
EU support to Morocco - Limited results so far
About the report:
This audit assessed the effectiveness of EU budget support to Morocco from 2014 to 2018. It covered budget support in the sectors in the health, social protection, justice and private sector development, looking at management by the Commission and evaluating the achievement of objectives. The Commission considered budget support to be the right choice of aid delivery instrument. However, we concluded that its added value and ability to support reforms was limited due to sub-optimal focus, weak implementation and insufficient monitoring. The main weaknesses related to indicator design and results assessment. We have therefore made recommendations on focusing support in fewer sectors, improving indicator design, enhancing the control procedures for disbursement and strengthening the policy dialogue.
ECA special report pursuant to Article 287(4), second subparagraph, TFEU.
Executive summary
IMorocco is a North-African country with steady growth and a stable political environment. The association agreement signed in 1996 strengthened the cooperation between Morocco and the European Union (EU). With the launch of the European Neighbourhood Policy (ENP) in 2004, Morocco gradually became a privileged partner of the EU in terms of political and economic cooperation as well as in trade, technical and development cooperation.
IIWe assessed the effectiveness of EU budget support (BS) in Morocco from 2014 to 2018. The EU BS in Morocco totalled over that period about 0.37 % of the country’s total budgetary expenditure. We examined the Commission’s management and the degree to which the EU budget support objectives had been achieved. The sectors covered were health, social protection, justice and private sector development. During the period under review, contracts for all sectors covered by BS totalled €562 million and payments €206 million.
IIIBased on an appropriate risk analysis and needs assessment, the Commission considered BS to be the right choice of aid delivery instrument. However, we concluded that its added value and ability to support reforms has been limited due to a sub-optimal focus, weaknesses in design and insufficient monitoring. In addition, donor coordination was uneven amongst the sectors.
IVAfter the judgement of the General Court of the EU in December 2015 on Western Sahara, Morocco suspended political dialogue from December 2015 until January 2019. The Commission did not use this standstill period to develop a clear strategy for its relations with Morocco. Although policy dialogue took place, it was not sufficient for all sectors. Furthermore, the Commission had not formalised strategies for policy dialogues.
VBS had not sufficiently supported reforms and progress on key challenges was limited. The Commission’s management was hampered by weaknesses in the design of the BS programmes and their indicators. We also found shortcomings in the monitoring procedures and the Commission’s results assessment.
VIEU support targeted cross-cutting issues such as gender and human rights. Despite this targeting, limited improvement could be observed for the period under review.
VIIWe made a number of recommendations for the Commission to strengthen the EU approach and the political and policy dialogue, improve the design of the indicators and the monitoring procedures, enhance the verification procedures for disbursements and increase the visibility of EU support.
Introduction
An important partner
01The Kingdom of Morocco is geographically Europe’s closest neighbour in North Africa (see Figure 1). Morocco was ranked 123rd out of 189 countries in the 2018 United Nations Human Development Index list and its human development is therefore considered medium. With an annual gross domestic product of around €101 billion (2018) and approximately 35 million inhabitants, Morocco is the fifth largest African economy and an important political and economic partner for the EU. Reciprocally, the EU is Morocco’s most important trading partner, representing around 65 % of its exports and 57 % of its imports1.
Figure 1
Morocco
Source: https://en.wikipedia.org/wiki/Regions_of_Morocco
Source: Eurostat
Morocco is benefiting from its prudent macroeconomic management and the structural reforms undertaken in recent years. Growth has continued at a relatively steady pace and inflation is low. The external deficit of the current account and the budget deficit have continued to decrease in recent years.
03Set against the background of the unrest in the region in the aftermath of the 2011 Arab Spring, Morocco enjoys a stable political environment. With its new constitution, adopted in July 2011, Morocco took important steps towards political modernisation and an open economy.
04This constitutional reform emphasised the importance of fundamental rights and gender equality. However, the national legislation is not yet fully aligned with the United Nations conventions on human rights. For example, the United Nations Human Rights Committee recommended abolishing the death penalty, combating violence against women, increasing gender equality, improving the protection of children’s rights, ratifying the Rome statute establishing the International Criminal Court and eliminating the criminalisation of homosexuals. Morocco rejected most recommendations linked to women’s rights2.
05The EU and Morocco have had a stable relationship since their first trade agreement was signed in 1969. The partnership has developed and matured over the years (see Annex I), leading to the signature of a general association agreement in 19963. This association agreement, which entered into force in 2000, represents the legal basis for EU-Morocco relations. Since the launch of the European Neighbourhood Policy in 2004, Morocco has gradually become a privileged partner of the EU in the field of political and economic cooperation as well as in trade, technical and development cooperation.
06In the context of the European-Mediterranean partnership, the association agreement took a turning with Morocco acceding to advanced status4 in 2008, underpinning the special nature of its relationship with the EU. This provided a framework for high-level political cooperation in order to bring Moroccan legislation further into line with EU legislation and gradually integrate the Moroccan economy into the EU internal market.
A major recipient of ENI funding
07Morocco receives more EU development support than any other North-African country, except Tunisia, and is one of the main beneficiaries of international development aid. The EU is its biggest donor, providing 25.2 % of official development assistance (see Figure 2).
Figure 2
Official Development Assistance (ODA) in Morocco in 2017, main donors ($ million)
Source: Organisation for Economic Cooperation and Development.
In addition to official development assistance, other development actors are also active in Morocco. The official statistics of the Organisation for Economic Cooperation and Development show for example that the World Bank (WB) and the African Development Bank (ADB) are important donors in the sectors of infrastructure projects and good governance, health and social protection.
09The European Neighbourhood Instrument (ENI) is the key financial instrument supporting the Commission’s cooperation with Morocco. The Commission programmes the EU’s bilateral support for a period of seven years. The overall amount committed fell from €1 431 million for 2007-2013 to €1 399 million for 2014-2020 (see Figure 3). The main priority sectors stated in the Single Support Framework (SSF) for 2014-2017 were equitable access to basic social services, support for democratic governance, the rule of law and mobility, and jobs, sustainable, inclusive growth.
Figure 3
Bilateral assistance commitments in North Africa
Source: European Commission.
Morocco is one of the biggest beneficiaries of bilateral ENI programmes in North Africa. From 2014 to 2018, the allocation for BS (see Box 1) resulted in contracts totalling €562 million and payments totalling almost €206 million (see Annex II). On average, BS constitutes 75 % of annual EU expenditure for Morocco. Morocco also receives additional funding under several thematic programmes and instruments (see Annex III) and EU support is also channelled via financial institutions and trust funds.
Box 1
The budget support modality
According to the Commission, BS is an effective means of delivering aid to support reforms and sustainable development goals. The Commission considers it to be a vector of change for improving public financial management, macroeconomic stability, sustainable and inclusive growth and the fight against corruption and fraud, and promoting sector reforms, human rights, democratic values and gender equality.
BS involves dialogue, financial transfers to the national treasury account of the partner country, performance assessment and capacity development, based on partnership and mutual accountability. The funds transferred are not earmarked for a specific purpose; it is therefore not possible to follow where and how they are used. Once the funds have been transferred, the partner country can use them in its normal budgetary process.
BS is not provided to every country. Eligi¬bility criteria have to be met before and during the programme and conditions need to be fulfilled before payments are made.
To be eligible for BS, a country must have:
- relevant, credible sectoral/national development strategies;
- a stability-oriented macroeconomic policy;
- a relevant, credible public financial management reform programme and
- budget transparency and oversight (budget information must be made publicly available).
In addition, a fundamental values assessment needs to be undertaken when BS contracts are proposed.
BS is paid in fixed and variable tranches. Fixed tranches have a fixed value, specified in advance within the financing agreement (contract between the beneficiary country and the Commission). They are disbursed in full (when all conditions are met) or not at all (if one or more conditions are not met). Variable tranches have a maximum value specified in advance in the financing agreement. They are either disbursed in full or in part with the amount disbursed being based on the perfor-mance achieved in relation to pre-specified targets or designated performance indicators (provided that at the same time the general conditions are all met). This performance assessment is based on data to be provided by the beneficiary country defined in the financing agreement (sources of verification).
Source: The Commission’s Budget Support Guidelines, September 2017.
The EU Delegation in Rabat and the Directorate General for Neighbourhood and Enlargement negotiations are managing and implementing the programmes. The European External Action Service (EEAS) and the EU Head of Delegation are responsible for the political dialogue.
Bilateral relations challenged
12The EU and Morocco have enjoyed long-standing good relations. However, the EU-Morocco partnership had been strained since 2015, when the General Court of the EU made the first series of rulings that Western Sahara was not a part of Morocco. This meant that Western Sahara was not part of the fisheries and agriculture agreement between the EU and Morocco and could not benefit from the same tariff preferences. The Western Sahara issue (see Box 2) put the EU-Morocco partnership under stress and Morocco suspended political dialogue.
Box 2
Summary Judgments of the Court of Justice of the European Union (CJEU)
10 December 2015: The judgment of the General Court of the EU5 annulled the Decision6 on the implementation of the agricultural agreement in the territory of Western Sahara. The judgment established that the agricultural agreement applied to Western Sahara, but that Western Sahara was not a part of Morocco, and that the Kingdom of Morocco was not the administering power. Before adopting the Decision, the Council should have ensured that the natural resources of the territory would not be exploited to the detriment of its inhabitants and their fundamental rights.
21 December 20167: The CJEU annulled the judgment of 2015 and ruled that no trade or association agreement with Morocco could apply to the territory of Western Sahara, since Western Sahara was not part of Morocco. Accordingly, the CJEU stated that the people of Western Sahara should be viewed as a third party to the EU's relations with Morocco. Therefore, as for any bilateral arrangement, the express consent of the people of the territory should be obtained.
February 20188: The CJEU held that, as Western Sahara did not form part of the Kingdom of Morocco, the waters adjacent to Western Sahara were not part of the Moroccan fishing zone referred to in the Fisheries Agreement.
First quarter 2019: The European Parliament and the Council approved an amendment to two protocols, for fisheries and agriculture. The aim was to foster economic development in Western Sahara by treating its exports to the EU in the same way as exports from Morocco.
Political dialogue is held at the level of the EEAS, the EU Head of Delegation and the Ministry of Foreign Affairs in Morocco.The policy dialogue is held at sectoral level between the EU Delegation staff and the Moroccan authorities. Figure 4 explains the difference between political and policy dialogue.
Figure 4
Political and policy dialogue
Political Dialogue |
Covers all EU external policies: development policy, trade, foreign and security policy |
In line with the EU treaties, European External Action or other legal bases |
In all countries, political dialogue usually takes place between the EU Head of Delegation and Ministerial level |
Policy Dialogue |
Covers the specific sectors of EU cooperation |
Should support the general and specific objectives of budget support contracts |
Support the partner’s country’s efforts to achieve the objectives laid down in their strategies. May carry a political dimension (e.g. when difficult reforms are politically costly). |
Source: DEVCO Academy.
Audit scope and approach
14This audit assessed the effectiveness of EU BS to Morocco for 2014-2018. We asked the following questions:
- Did the Commission and the EEAS choose the priority sectors appropriately and design the programmes well?
- Did the Commission implement EU support appropriately in Morocco?
- Were the objectives of EU support to Morocco achieved?
The audit covered the period from the official decision setting up the European Neighbourhood Instrument (1 January 2014) up to the end of 2018. The audit focused on this period, as an external evaluation on BS to Morocco had already been carried out for the period 2005 to 2012 (published in 2014). Furthermore, this period is in line with the ENI-programming period. Amounts contracted and paid for this period are material. In addition, the Commission has not yet carried out a country evaluation covering support to Morocco.
16The audit was carried out from September 2018 to February 2019, covering health, social protection, justice and private sector development (PACC: ‘programme d’appui à la croissance verte et la compétitivité au Maroc’). The majority of the ENI expenditure in Morocco between 2014 and 2018 was in these sectors (see Annex II)9. In addition to the BS programmes in these four sectors, we reviewed the 10 projects relating to the corresponding financing decisions (see Annex IV). We examined whether gender and human rights were addressed as cross-cutting issues in these BS programmes. Annex V summarises the objectives of the BS programmes audited and Annex VII provides an assessment by sector.
17Our audit work consisted of a desk review, interviews with staff from the Commission Headquarters and the EEAS, and an on-the-spot visit. The visit enabled us to collect further information and interview representatives of the national authorities and staff at the EU Delegation and representations of EU Member States in Morocco (Spanish and French representations). We also interviewed international organisations and other donors, such as the World Bank, the ADB, Unicef and the Deutsche Gesellschaft für Internationale Zusammenarbeit. In addition, we visited beneficiaries including a detention centre for girls, a social protection centre and private companies that had received investment subsidies.
18As one of the EU’s largest beneficiaries of external aid, Morocco is a strategic partner in key policy areas. The Commission can benefit from the conclusions and recommendations of this report by taking them into account for the next programming period (as from 2021). The relevance and potential impact of this report are therefore high.
Observations
Focus and design of the support were sub-optimal
Budget support spread too widely to maximise results
19We looked at whether the Commission and the EEAS had consistently prioritised sectors for BS based on Morocco’s main needs. We checked whether an adequate needs assessment had been carried out. We also considered whether the Commission had coordinated its approach appropriately with other donors active in Morocco.
Budget support was based on an appropriate risk/needs assessment
20The Commission considered BS to be the most appropriate instrument for supporting and sustaining the implementation of national and sectoral reforms. The Commission performs an annual risk analysis for the following categories: political governance, macroeconomic stability, development, public financial management and corruption/fraud. The eligibility criteria were clearly met at the design phase, and the fundamental values were not considered high risk. Morocco’s risk level was assessed as moderate.
21According to the Commission’s risk analysis, however, one of the main residual risks concerned corruption. In the absence of an anti-corruption body, the Commission was not able to address corruption through this avenue. This meant that the Commission addressed corruption through some of its BS programmes. For example, the digitalisation of procedures in the PACC programme is contributing to reducing corruption as well as measures and indicators in the health and social protection BS programmes. In the justice programme, the organic law contains measures aimed at reducing corruption. However, some of these, such as the code of ethics for judges, had not yet been adopted.
22The country reports of the International Monetary Fund and the Public Expenditure and Financial Accountability assessment of 2016 did not reveal major deficiencies and were in line with the Commission’s risk assessment.
23The Commission had carried out a detailed needs assessment for the specific BS programmes in cooperation with the national authorities and consulted a wide range of stakeholders during programme formulation. The EU Delegation had also met with civil society organisations. However, the Moroccan Court of Auditors (which is an important stakeholder) was not consulted during the needs assessment for the sectors audited.
24The BS programmes were complementary to other EU support, and coordination, in the form of bilateral and thematic programmes, was good. Technical assistance was included in the design of all BS programmes. The total proportion of complementary cooperation instruments (technical assistance, twinning, etc.) supplementing BS in Morocco had increased over time, from 5 % (2007-2010) to 13 % (2011-2013), then to 16 % (2014-2016) and then further to 18 % (2017-2018).
Important needs addressed but funding covered many areas
25When programming bilateral support for Morocco, the Commission had addressed numerous priority areas. These areas responded to needs covered by sectoral strategies and reflected in both the national government plan and the EU action plan. In the programming documents, the Commission had demonstrated clearly why sectors required funding. The priority sectors remained the same for 2007-2013 and 2014-2020 (see Figure 5).
Figure 5
Overview of priority sectors 2007-2020
2007-2013 | 2014-2020 | |
Sector 1 | Social policy development €412 million | Equitable access to basic social services €441 million |
Sector 2 | Governance/Human rights €115 million | Support to democratic governance, the rule of law and mobility €337.5 million |
Sector 3 | Modernisation of the economy €298 million | Jobs, sustainable and inclusive growth €367.5 million |
Capacity building | Institutional support (incl. Réussir le Statut Avancé) €272 million | Complementary support for capacity development and civil society €294 million |
Other | Environment €137 million | |
Total | €1 234 million | €1 470 million |
Source: Indicative programmes 2007-2010, 2011-2013 and SSF 2014-2020.
The Commission had defined the three priority sectors too broadly, as they consisted of 13 sub-sectors10, many of which could be considered as standalone sectors. There was therefore scope for reducing aid fragmentation. In addition, focusing on too many sectors reduces the potential impact of EU support. The agenda for change11 states that the EU shall engage in no more than three sectors per partner country to increase the impact and leverage of its assistance.
27The amount allocated to each programme depended on a number of parameters12. Amounts allocated were based on negotiations, which were not documented. Therefore, the Commission was unable to demonstrate that the amounts had been allocated using a transparent method.
The Commission had not developed a clear strategy for future relations with Morocco during suspension of political dialogue
28The CJEU judgment and institutional blocking after the parliamentary elections had a limited but noticeable impact on cooperation (see Box 2).
29The initial CJEU judgment was issued in December 2015. The negotiations relating to the Deep and Comprehensive Free Trade Agreement, the Migration and Mobility Partnership and Security/Counter Terrorism cooperation had not progressed since then.
30The Association Council13 is meant to meet annually to review bilateral relations and evaluate the progress of the implementation of the association agreement. However, there were no meetings between December 2015 and June 2019. Therefore, the last available progress report drafted by the EEAS related to 2014 activities. However, the EU Delegation continued to provide regular political reporting.
31Morocco’s advanced status had been extended to the end of 2018 and a further extension to the end of 2020 was being considered. In addition, Morocco had requested a complete review of bilateral relations with the EU, with a new, tailor-made framework going beyond the advanced status.
32In the absence of a formal political dialogue, the Commission had not addressed new priorities and/or challenges, anticipating the expiry of the SSF. In recent years, the EU Delegation had reacted to requests from the Moroccan Government on the basis of the existing SSF instead of using the political standstill to re-assess its operational priorities with Morocco and develop a clear, forward-looking strategy. The Commisssion and the Member States considered that the SSF priorities were still relevant and thus extended the 2014-2017 SSF to 2018. For 2019-2020 there would be no new partnership priorities. Instead, there would simply be a short-term framework similar to the current SSF which can serve as a legal basis for 2019-2020 programming.
33The Commission did not suspend BS as the EU financial regulation, the BS guidelines, and the provisions of the financing agreements do not provide for the suspension of BS in the absence of political dialogue. Payments relating to BS continued as programmed and were higher in 2016 and 2017 than in the two preceding years (see Figure 6).
Figure 6
BS payments for Morocco during 2011-2018
Source: DEVCO Data Warehouse.
Donor coordination was uneven
34During the identification phase, the EU assesses which other projects are ongoing in the sector and holds meetings with the technical and financial partners to ascertain ongoing/planned financing in the sector. The ‘Groupe Principal des Partenaires’ had met every two months since 2016 to discuss sectoral issues at strategic level. However, not all donors in Morocco had met regularly (e.g. China and India).
35In Morocco, there was a wide range of donors in most sectors. However, there was a lack of consistency between Member States’ objectives/priorities and those of the EU. Although the process of joint programming was introduced in 2014, Member States did not implement it until 2017, when agreement was reached over how to implement it in three sectors (migration, gender and vocational training). This was because Member States were keen to maintain their own visibility. The large number of sectors and donors involved did not contribute towards aid effectiveness.
36Some sectors had effectively established arrangements for donors, particularly the health sector where objectives and performance assessment frameworks were shared. The Commission chaired the financial and technical partner group for health and social protection. For the PACC, there was no formal donor meeting group, but there was one coordination platform: the G20 Compact with Africa.
37In the justice sector, formal meetings did not take place between the donors between 2015 and 2017. As the Ministry of Justice has ensured coordination of this sector since 2017, meetings have been organised with the technical and financial partners but only once a year, even though partners had expressed a wish to meet at least twice a year in order to avoid overlaps. There was little documentation of these meetings. The steering committee required by the financing agreement to ensure coordination between the ministries and the programme partners, had not been created.
38For the sectors audited where both the EU and other donors were providing support, there were very few joint indicators. While in the health sector 11 of the 18 indicators were similar to those used by the World Bank, in the PACC programme there were seven similar and in the social protection programme, there was only one. Annual assessments and evaluations were not shared systematically for the sectors audited.
Budget support programmes not designed to maximise impact
39We verified if the BS targets and indicators were aimed at supporting reforms.
A number of budget support targets not ambitious enough to support reforms
40Although BS programmes were aligned with the country’s sectoral strategies, not all strategies had quantified targets for specific objectives or action plans. Consequently, it was not always possible to compare the targets of the BS programmes with national sectoral targets. However, as from 2019, the Budget Law requires ministries to accompany budget projections with performance targets set against their main strategic policy objectives.
41The indicators related to the creation of institutions, drafting legislation and national plans did not focus on outcomes.
42We found that 25 of the 86 BS targets were not ambitious enough to support reforms. For example, in the health sector, the main problems were insufficient medical staff and disparities between urban and rural areas. However, the BS programme focused mainly on reducing disparities between rural and urban areas and addressed the lack of human resources through only one target of the variable tranche which was not very ambitiousaiming to train just 13 doctors as “family doctors” over a period of two years.
43Some of the challenges identified by various stakeholders (Ministry of Health, World Bank, etc.) in the health sector had not been directly addressed in the design of the BS programme: high staff absenteeism, low attractiveness of remote areas for medical staff and the structural underuse of hospital infrastructure.
44In the social protection sector the target of bringing 25 % of social protection centers into line with the new law was not ambitious since it had already been achieved, as a higher percentage than this already met the stricter requirements of the previous law.
45In the justice sector, the objectives, although broad, were in line with the objectives of the reform, for instance aiming for an independent sector and the judicial protection of rights and freedoms.
46The PACC was built on three strategies, two of which were lacking time-bound objectives, making it difficult to define the most important/urgent needs. The programme covered too many sectors, providing support for small and medium-sized enterprises (SMEs), start-ups, land tenure, trade, sustainable development and energy.
Indicator design did not enable objective performance measurement
47The Commission assessed Morocco’s monitoring and evaluation systems when designing BS programmes. In the absence of a framework assessment for evaluating sectoral progress, it applied existing guidelines. With the exception of the health sector, sectoral strategies were not always accompanied by a fully-fledged action plan, with baseline data, results indicators and pre-defined targets.
48We noted the following weaknesses in the selection and use of indicators:
- Indicators of the variable tranches were not appropriate to monitor progress of the specific objectives.
- Nearly all indicators related to outputs or process (e.g. the proposal to draft a law), not to outcomes.
- Two indicators were not sufficiently relevant as they did not measure the BS programme objectives. In the health sector, two indicators were related to the expected result ‘reduce disparities between urban and rural environments’. Both indicators reflected an absolute value, i.e. ‘increase in diabetic patients treated in rural areas’ and ‘increase in hypertensive patients treated in rural areas’. While an increase could mean that more patients in need were being treated (positive increase), it could also mean that the two conditions had become more prevalent in Morocco (negative increase). In any case, the indicators were not oriented towards measuring a decrease in disparity.
- Indicators frequently had inaccurate baselines or none at all14. An accurate starting point is necessary for measuring progress and assessing whether targets are both realistic and sufficiently ambitious.
- Indicators had outdated baselines and targets15. The programming process took about a year, so baselines no longer reflected reality and targets had sometimes already been achieved or were nearing achievement when the financing agreement was signed16. Failing to update baselines and targets when signing the financing agreement resulted in payments being made where development had deteriorated instead of improved.
Difficulties in implementing support
Delays affected implementation
49We examined whether the activities had been implemented as planned and outputs delivered as intended.
Outputs and complementary support not always delivered on time
50Overall, implementation of reforms did not always take place as planned in the sectors audited. Delays were mainly due to legislative proposals not being approved in time (social protection), the fact that Parliament had not yet adopted the penal law and penal procedure code (justice), the lack of a dedicated action plan (health) and the limited policy dialogue with the private sector (PACC).
51As the implementation of reforms was delayed in the justice and PACC sectors, several of the disbursements were also later than originally planned. Despite the delay in social protection activities during the first year of implementation, the Commission did not consider it necessary to take corrective action as technical assistance was in place from previous BS programmes. The Commission had extended the PACC programme by one year and the justice programme by two years. The initial duration of the programmes was four years (and five for the justice programme).
52In the sectors audited, the BS programmes were complemented by technical assistance and twinning (between 2 % and 13 % of the BS amount). Although this complementary support provided in the sectors audited was in line with the objectives of the BS programmes, it frequently started two to three years after the financing agreements were signed. Consequently, it did not reinforce BS appropriately.
Limited evidence of sector policy dialogue
53We checked whether the Commission had a structured approach to policy dialogue that included setting clear objectives, interacting frequently with the Moroccan authorities and keeping progress logs.
54Policy dialogue is an essential activity under BS. It is one of the main components of BS contracts, alongside the transfer of funds and capacity strengthening. It is expected to contribute towards achieving the objectives of BS programmes.
55Despite the suspension of the political dialogue, the sectoral (policy) dialogue had continued between the EU Delegation and some ministries (e.g. Health and Social Development). However, the EU Delegation did not have a formalised policy dialogue strategy with clear objectives. There was no evidence that the dialogue addressed adherence to national sectoral strategies and documentation of the meetings held was poor. Meetings took place on an ad-hoc basis, taking into account the needs of both sides. For justice and PACC, the dialogue was minimal.
56The Ministry of Foreign Affairs had advised the other ministries not to communicate openly about any EU support. Contacts between the ministries and the EU Delegation did not always take place at the appropriate level.
Poor results assessment by Commission
57We examined whether the Commission had monitored the implementation and performance of the programmes appropriately and whether the conditions for disbursements had been met.
Variable tranches often paid when conditions were neither met nor verified
58The disbursement of the variable tranches17 was based on sources of verification stipulated in the financing agreement and agreed at design stage between the Commission and the ministries, as well as other official sources provided by the government. Nevertheless, several sources18 of verification stated in the financing agreement did not exist or the ministries did not provide them.
59In our sample of 54 targets, the Commission considered 33 of them to have been achieved. We looked at how the Commission assessed whether indicators had been achieved before making payments and observed that19:
- The Commission made payments based on the achievement of 10 targets without checking the reliability of the data used for verifying this. For example, two disbursements under the PACC were made on the basis of the number of self-employed people, although the EU Delegation had not checked the accuracy of the database used. The main criterion used was self-employed people declaring themselves as such, but this was not sufficient, since this declaration is voluntary. Ministry of Finance data showed that the number of self-declared self-employed people was roughly double the number of self-employed individuals who declared their income for taxation.
- The Commission made payments for seven targets achieved on the basis of baselines which were not up to date. For example, the baseline for an indicator relating to childbirth used for payments made in 2017 took 2012 figures as the baseline for a BS programme signed in 2015. However, had 2014 been used as a baseline, as childbirth was higher, it would have been clear that the situation had deteriorated, and BS payments would have been lower.
- The Commission paid for five targets without having set an initial baseline to compare progress to. In a further six cases, disbursements were made based on inappropriate calculations. For example, the number of diabetic patients treated was calculated without adjusting for the situation before EU support began.
- In 15 cases, the Commission paid for targets on which no progress had been made or when targets were not achieved. For example, one target was to increase the number of general practitioners in rural primary healthcare centres. Although the number decreased, the Commission paid the support. As a consequence of the Court’s audit, for two of these targets, the Commission has however initiated the necessary steps to recover the amount paid.
A total of around €88 million was paid in relation to variable tranches for the sectors audited. However, the lack of rigorous controls when assessing results had a financial impact of €6.79 million. Furthermore, regular payments amounted to €19.9 million, although the corresponding indicators were not contributing to the objectives of the BS programme. In addition, an amount of €15.28 million was paid out, although no sufficient checks were performed or inappropriate sources of verification were taken into account. Annex VI contains a detailed overview by sector.
61In addition, €14.64 million was carried over although the conditions for carry-over stated in the financing agreement were not met. The Ministries of Social Development and Justice had asked to carry over to the following year the evaluation of five indicators (representing €10 million) and three indicators (representing €4.64 million), respectively. However, the Ministries did not provide any written justification for this, nor was the delay related to external factors.
The Commission did not always monitor progress thoroughly
62The advanced status granted to Morocco is of high political importance and constitutes an overarching framework for EU-Morocco relations. Its aim is to reinforce the relationship. However, there was no formal evaluation of the results achieved or areas covered.The Commission plans to perform a country evaluation in 2019 on the ‘EU support/assistance in Morocco’.
63External experts paid by the Commission carry out field visits for each BS programme twice yearly and at the end of each BS programme. The follow-up of the recommendations is not systematically reflected in their reports.
64The EU Delegation monitored programmes mainly when making payments related to the achievement of indicators. This was often too late to allow for the necessary corrections to be made when there were delays. However, in the justice sector, the EU Delegation did not carry out sufficient monitoring at operational level, which had an effect on the payment of the variable tranche (see Box 3).
Box 3
Weaknesses in the Commission’s monitoring procedures
As part of our audit of the justice sector, we planned to visit three locations funded through indicator three of the BS programme, which aims at the rationalisation of the judicial map: the Court of Appeal in Guelmim, the Court of First Instance in Sidi Ifni and the Judicial Centre in Taghjijt.
The targets related to the disbursement for this indicator at the end of 2017 were the adoption of a law proposal on the rationalisation of the judicial map20 and the implementation of 60 % of this reform as regards the judicial centres21.
The objective of our on-the spot visit in January 2019 was to check the effective implementation of the law and of the decision on the judicial centres. Six weeks after we had informed the EU Delegation of our planned visit, we were informed that none of the three buildings were operational.
This indicates that the EU Delegation had not carried out field visits and had made payments solely on the basis of a legislative proposal and a ministerial decision.
No significant impact for budget support programmes
Budget support objectives only partially achieved
65At the time of our audit, the BS programmes and related technical assistance contracts were still ongoing. We examined the extent to which the targets set for the BS programmes had been achieved. We assessed progress towards achieving the objectives of BS in the four sectors we examined for our audit as well as any links between this progress and EU support.
Less than half of budget support targets met
66A majority of the targets of the BS programmes had not yet been achieved, but the BS programmes and related technical assistance contracts were still ongoing. Our assessment differs from that of the EU Delegation with regard to the achievement of targets. According to the EU Delegation, out of 54 targets, 62 % had been achieved by the end of December 2018, whereas we found the achievement rate to be 40 % (see Figure 7). The Commission had assessed several of the unachieved targets as low risk during the design phase.
Figure 7
Achievement of targets
BS Sector | Targets | Targets achieved – EU Delegation | Targets achieved – European Court of Auditors |
Health – first variable tranche | 11 | 7 | 5 |
Health – second variable tranche | 10 | 5 | 4 |
Social Protection – first variable tranche | 9 | 3 | 1 |
Justice – first variable tranche | 9 | 6 | 3.5 |
PACC – first variable tranche | 10 | 8 | 5 |
PACC – second variable tranche | 5 | 4 | 3 |
Achievement rate | 54 | 62 % | 40 % |
Source: European Court of Auditors.
Despite some improvements in the health sector (see paragraph 76), some important indicators of the BS programme had not yet been achieved: better access to health centres for the rural population, increase in the number of women giving birth in these centres, improved availability of medicines in health centres and health inspectors in every region.
68For the social protection sector, five out of nine were process indicators and hence affected by the legislative delays (see paragraph 50). With regard to the results indicators, the following crucial targets had not yet been achieved: three-year budget plan for the social services sector, global medical coverage for employees and medical coverage for non-salaried workers.
69For the justice sector, two process indicators were affected by the delay in the approval of the penal code. With regard to the results indicators, only one of the eight judicial centres to be activated was operational. It is impossible to assess whether or not the target relating to judicial assistance had been achieved, as the source of verification used to identify the beneficiaries (RAMED cardholders) was not appropriate.
70According to the EU Delegation, most of the PACC targets had been achieved. However, due to a lack of documentation or the absence of checks by the EU Delegation, there was no proof of the achievement of five indicators at the time of payment (see Annex VI).
71Despite the extensions for indicator assessment granted by the EU Delegation (see paragraph 51), target achievement was still low. In addition, in 2018, the Commission set less ambitious targets for five indicators in the justice sector, dropped one PACC indicator and reduced the targets of two others. As such, the Commission reduced the conditions for achievement.
Budget support had not sufficiently supported reforms
72BS funds in Morocco are not linked to a specific budget line. According to the Commission22, this had generated growing discontent in some ministries due to the feeling that their efforts were not (or not always) rewarded with additional budgetary outlays. Although the national authorities favour BS as an aid delivery method, the sectoral ministries do not notice its added value, preferring to receive technical assistance as this is more tangible. Furthermore, up until 2018 there had been no multiannual budgetary forecasts. As from 2019, there is a three-year budget plan, which could be aligned with the multiannual BS programmes.
73Although the budgetary executions rates were satisfactory, significant amounts remained to be spent in the budgets of the ministries audited for 2014-2016, and also for 2017 in the case of the Ministry of Industry (see Figure 8). The ministries’ annual budgets had not substantially increased, and had even fallen in the case of the Ministry of Energy (see Figure 9). This puts the added value of BS into question.
Figure 8
Yearly unspent budget
Source: EU Delegation.
Figure 9
Ministerial budgets 2014-2018
Source: European Court of Auditors.
Moreover, EU BS only represents a fraction of the country’s gross domestic product, thereby limiting its overall leverage (see Figure 10).
Figure 10
Budget support as % of Moroccan GDP and budgetary expenditure
Period | Morocco’s nominal GDP (million euro) | Morocco’s general budgetary expenditure (million euro) | EU BS (million euro) | % EU BS/ Morocco’s GDP | % EU BS/ Morocco’s budgetary expenditure |
2014 | 82 800 | 33 970 | 65.0 | 0.08 | 0.19 |
2015 | 91 200 | 35 400 | 115.98 | 0.13 | 0.32 |
2016 | 93 300 | 35 980 | 163.9 | 0.18 | 0.46 |
2017 | 97 300 | 36 800 | 164.2 | 0.17 | 0.47 |
2018 | 100 500 | 37 680 | 153.3 | 0.15 | 0.41 |
Source: EU Delegation.
For the PACC programme, only little statistical data for Morocco is publicly available. The reports provided by the national authorities do not allow sectoral progress to be monitored appropriately. For instance, the EU Delegation lacked annual statistics for a number of key figures to monitor the industrial acceleration plan. Consequently, it is difficult to determine the added value of the programme.
Health
76Limited progress had been made towards the objectives of the health programme. Access to primary healthcare was still not equal as the differing conditions between the public and private sector, and between urban and rural environments, had not been addressed sufficiently via the indicators in the BS programme.
77There was not sufficient emphasis on improving the skills of healthcare workers or attracting more medical students in the health sector. Furthermore, the specific objective of setting up an integrated, accessible electronic healthcare information system had not been achieved. BS can better address the main root causes (i.e. ratio of medical staff per inhabitant and disparities between urban and rural environments) in the long term, whereas its short term impact will remain limited.
Social Protection
78EU support had prompted reforms in the social protection sector, but, given the early stage of the BS programme it was too early to see an overall impact. The BS led to the formulation of a single sector policy on social protection. However, policy implementation was affected by legislative delays.
79A positive effect of the BS programme is that the introduction of individual social security numbers will be linked to an impact evaluation concerning the Tayssir23, Régime d’assistance Médicale and DAAM24 programmes. Thanks to this individual social security number, only eligible beneficiaries will benefit from these programmes, which will have a significant effect on programme costs. In addition, the social security number will be the starting point for all social services. In the near future, an anti-fraud component will be added to the individual social security number (via technical assistance provided by the EU).
Justice
80The Moroccan government had already initiated reforms in 2011, but given the complexity of these reforms, implementation was slow, especially for the penal code, which has been under parliament scrutiny for over two years. The reforms are however particularly important as regards the protection of human rights (detention conditions, etc.). According to Freedom House25 reports26, the justice sector is not yet considered independent.
81The International Commission of Jurists pointed out in one of its reports27 that investigative judges and prosecutors routinely disregard provisions of the Code of Criminal Procedure that provide for pre-trial detention to be used only in exceptional cases. In 2017, 42 % of prisoners were held under preventive detention. It also confirms the reports by Freedom House, stating that police custody procedures fail to comply with Morocco’s obligations under international law.
82Overall, there had been limited progress towards the achievement of the objectives of the BS programme: an independent justice sector, improved access to rights and justice, increased judicial protection of rights and freedoms and an increase in the effectiveness and efficiency of the justice sector.
PACC
83In general, Morocco’s competitiveness was improving, with an increase in exports, GDP growth, an increase in foreign direct investment and a reduction in the current account balance deficit. Morocco had also risen 27 places in the World Bank’s ‘Doing Business’ index between 2014 and 2019 (see Annex VII). Box 4 shows a positive achievement linked to the PACC programme.
Box 4
PACC: Promoting paperless procedures
Morocco’s aim is to achieve a paperless trade system by 2021. A solely digital supply chain will make stakeholder procedures clearer, reducing time and costs.
- The PACC programme is supporting the digitalisation of trade procedures via six indicators and the reform process.
- Online communication and digital document exchange have contributed to customs efficiency. Since 1 January 2019, the customs clearance system has been entirely paperless.
- In the past year, Morocco has moved up nine places in the World Bank’s ‘Doing Business’ index.
There was also a strong political will to implement the industrial acceleration plan28. According to the Organisation for Economic Cooperation and Development, despite the high number of reforms and the support for start-up and innovation, more international companies than SMEs had been set up in Morocco.
85The informal sector is extensive in Morocco (around 2.38 million business units29). Consequently, even if the PACC were to formalise 45 000, this would not be significant. Nor is there any guarantee that ‘auto-entrepreneurs’ officially register their activities after obtaining the relevant card (see paragraph 59, point (a)). PACC support is limited to 250 SMEs, whereas there are about 735 000 SMEs in Morocco.
86In addition, only 100 export companies with a turnover below 5 million dirham (approximatively €460 000) received support. The current ceiling (5 million dirham) meant that 4 260 companies were potentially eligible (i.e. 69 % of the export companies). As the goal was to support smaller companies and funds allowed to support only 100 companies, it would have been sensible to set a lower ceiling.
Acknowledgement of EU support not sufficiently visible
87Visibility of the EU’s financial cooperation, in particular as regards the results achieved, was insufficient. For example, no joint press releases were issued and there were no signs acknowledging EU support. While the political dialogue was suspended, the Ministry of Foreign Affairs had asked the other ministries not to communicate openly about any EU support received.
88The social protection programme had a condition in the financing agreement relating to communication and visibility. The health programme had a specific budget line dedicated to visibility. However, events in the health sector were only organised as from 2019. An additional indicator, ‘Reinforce communication on the reform of the justice sector and the visibility of EU support’, had been added to the justice programme via an addendum on 20 December 2018, with a deadline for achievement of 31 December 2018. However, the conferences on the reform of the justice sector had already been organised before the addendum was signed, and it was mainly the Ministry of Justice that benefited from the increased visibility.
89The PACC financing agreement included a communication and visibility condition. The ministry was required to draft and submit a communication plan as a condition for disbursement of the first variable tranche. The ministry also had to provide a report on the implementation of the communication plan before or upon submitting its request for disbursement of the next variable tranche. The ministry had provided a plan, which was approved by the Commission, but none of the proposed actions was implemented by the end of December 2018. This did not entail any financial consequences for the ministries.
90The EU logo did not appear on beneficiary websites for the programmes audited. Consequently, the visibility of EU support to Morocco did not reflect its presence as one of the biggest donors.
Limited progress on key challenges
91We examined whether the BS programmes made a positive contribution to cross-cutting issues and regional disparities.
There is evidence that poverty reduced but not social disparities
92The poverty level30 in Morocco had decreased significantly since 2001 (see Figure 11), although no data was available beyond 2014. Despite this reduction, there was no evidence that social disparities had improved, neither at national, urban or rural level.
Figure 11
Evolution of poverty level in Morocco during 2001-2014 (in %)
Source: World Bank.
A comparison of the Gini coefficient31 (2010-2017) for Morocco and all other middle-income countries for which data was available, as well as other recent studies, such as the one carried out by the Organisation for Economic Cooperation and Development and the African Union32 indicates that social disparities in Morocco remained high. However, Morocco’s performance was average compared to other middle-income countries (see Figure 12).
Figure 12
Gini coefficient - Morocco and middle-income countries
Source: World Bank.
Limited improvement in gender equality and human rights
94Although Morocco has made advancements in women’s rights over the last two decades, it still ranks 137th out of 149 countries according to the 2018 World Economic Forum’s Global Gender Gap Report. Morocco’s 2011 constitutional reforms included several proposals to increase women’s political and economic participation. Despite these pronouncements, women remain underrepresented in managerial positions, leave school at younger ages than male students, and are still an underutilized economic resource in Morocco.
95EU support targeted cross-cutting issues such as gender and human rights as follows:
- The EU action plan (advanced status) had a strong focus on gender equality, as did the SSF. The Commission monitored the expected results through the annual reporting exercise on the Gender Action Plan.
- Morocco is the only country that benefits form a dedicated BS programme on gender equality. Despite the mixed results of the 2012-2016 BS programme, with only 48 % disbursed, a new programme was launched for 2018-2020. The evaluation of the first gender-related BS programme revealed that, due to the lack of results indicators, the gender programme had a limited effect on other sectors. In addition, gender mainstreaming could have been carried out more effectively and gender-based economic disparities had not decreased.
- Gender had been taken into account in BS for social protection (two out of 15 indicators), justice (two out of 10 indicators) and health (three out of 18 indicators). For the PACC programme, the EU Delegation had not managed to have it included, as the ministry was against including it.
- Human rights had only been specifically addressed in the justice sector (three out of 10 indicators), but none of these targets had been achieved so far.
Despite this targeting, no improvement could be observed for the period under review. Moreover, the EU’s assessment of fundamental rights indicated that the situation had not improved since 2014.
97The limited progress in gender equality is confirmed by data from the United Nations Development Programme with regard to the gender inequality index33 and the human development index (HDI)34 for men and women (see Figure 13).
Figure 13
Gender inequality in Morocco
Source: United Nations Development Programme
Freedom House also confirms the negative situation in Morocco with regard to human rights (see Figure 14). The main issues they mention are the restrictive press laws, lack of internet freedom, failure to allow free assembly, and the lack of independence of the justice sector. In 2018, the score for Morocco’s civil liberties declined due to harsh state responses to major demonstrations throughout the year. Morocco is considered ‘partially free’ (see Figure 15).
Figure 14
Freedom House Index in Morocco
Source: Freedom House.
Figure 15
Human Rights in Morocco
Aggregate score: 0 = least free / 100 = most free
Source: Freedom House.
Conclusions and recommendations
99The audit examined the effectiveness of EU BS to priority sectors in Morocco. Based on an appropriate risk analysis and needs assessment, the Commission considered BS to be the right choice of aid delivery instrument. However, we concluded that its added value and ability to support reforms was limited due to sub-optimal focus, weak implementation and insufficient monitoring.The main weaknesses related to indicator design and results assessment. Not all expected outputs were delivered, nor were disbursements always based on the achievement of targets. Donor coordination was uneven. Moreover, there was no evidence that BS had supported the effective implementation of reforms.
100The Commission addressed needs identified in national and EU strategies. However, we found that the three priority sectors were too broadly defined, meaning BS was distributed across too many areas. This could weaken its impact (see paragraphs 25 and 26). The Commission had not used a transparent method to allocate amounts to sectoral BS programmes (see paragraph 27). The Commission had not used the political standstill to reassess its operational priorities for Morocco and develop a clear strategy (see paragraphs 32 and 33). With regard to donor coordination, Member States were keen to maintain their own visibility instead of aligning their objectives with those of the EU (see paragraph 35). Furthermore, very few joint indicators, missions or evaluations were in place between the EU and other donors for the sectors audited (see paragraph 38).
Recommendation 1 – Strengthen the focus of EU budget support in MoroccoFor the next single support framework, the Commission and the EEAS should:
- reduce the number of sectors and prioritise them in order to take into account the objective of maximising the impact of EU assistance;
- apply a more transparent and better documented method to allocate amounts to sectoral BS programmes;
- reinforce joint programming with Member States to increase aid coordination and effectiveness.
Timeframe: June 2021
101The Commission had not developed fully-fledged action plans with baseline data, results indicators and pre-defined targets. We noted weaknesses in the selection and use of indicators, as well as the use of output instead of outcome/impact indicators and outdated or missing baselines (see paragraphs 47 and 48).
Recommendation 2 – Improve design of targets and performance indicatorsThe Commission and the EEAS should strengthen its use of conditionality by:
- defining specific and relevant performance indicators with ambitious targets to support reforms and demonstrate progress/results;
- making greater use of outcome-oriented indicators;
- setting clearer, more relevant and more up-to-date baselines for all indicators.
Timeframe: December 2020
102The EU Delegation had not formalised policy dialogue strategies with clear objectives, nor were the meetings with the ministries systematically documented. Contacts between the ministries and the EU Delegation did not always take place at the appropriate level (see paragraphs 54–56).
Recommendation 3 – Strengthen policy dialogueThe Commission and the EEAS should strengthen their policy dialogue framework by adopting a policy dialogue strategy for all areas in which the EU provides support. This requires:
- a clear and appropriate definition of the objectives and expected results of the dialogue;
- minutes should be drafted;
- assessments of the achievements of the policy dialogue strategy.
Timeframe: December 2020
103The Commission’s assessment of the achievement of indicator-related targets was hampered by weaknesses such as payments made without verifying the reliability of the data, inappropriate calculations, payments made when targets had not been achieved and disbursements made despite a lack of progress. In addition, € 14.64 million was carried over to the next financial year, although the conditions stipulated in the financing agreement were not met (see paragraphs 58–61).
Recommendation 4 – Enhance disbursement verification proceduresThe Commission should enhance its payment verification procedures by:
- applying appropriate calculation methods (where relevant);
- disbursing funds only when there is reliable evidence that the target has actually been achieved;
- carrying over targets and related payments to another period only when beneficiaries have provided justification that the delays were due to external factors.
Timeframe: December 2020
104We found weaknesses in the Commission’s monitoring of BS operations. For example, the Commission monitored programmes mainly when making payments related to the achievement of indicators, which was often too late to allow corrections to be made when there were delays (see paragraphs 47 and 62–64).
Recommendation 5 – Improve monitoring proceduresThe Commission should improve the monitoring of its BS operations by:
- making greater use of field visits when monitoring programmes;
- strengthening assessments of sectoral strategies and monitoring their implementation using the indicators of the sectoral strategies;
- formally following up recommendations made by external experts and implementing those that are considered relevant.
Timeframe: December 2020
105Less than half of the BS targets had been achieved (see paragraphs 66–71). Although progress had been made towards the objectives of the BS programmes in the sectors audited, it was limited (see paragraphs 72–86). The implementation of ministries’ budgets had improved, but significant amounts remained to be spent. This puts the added value of BS into question (see paragraphs 73–74).
106Visibility of EU support in Morocco was insufficient. The social protection BS programme had a general condition relating to visibility. The required action plan stipulated in the PACC financing agreement had been drafted, but not implemented. In the justice sector, an indicator relating to visibility had been added at a later stage, but targets had already been achieved when the addendum was signed. In the health programme, a budget was provided for visibility, but events only took place as from 2019 (see paragraphs 87–90).
Recommendation 6 – Increase visibility of EU supportThe Commission and the EEAS should stipulate visibility conditions or indicators in its BS programmes in order to ensure that the EU support provided in Morocco is publicised. This should be a mandatory condition for disbursement in the financing agreement.
Timeframe: June 2020
107EU support targeted cross-cutting issues such as gender and human rights. Despite this targeting, only limited improvement could be observed for the period under review. (see paragraphs 94-98).
This Report was adopted by the Court of Auditors in Luxembourg at its meeting of 14 November 2019.
For the Court of Auditors

Klaus-Heiner Lehne
President
Annexes
Annex I – Important EU-Morocco cooperation phases
Source: European Court of Auditors.
Annex II – Budget support programme decisions, contracts and payments (2014 to 2018)
[European Neighbourhood Instrument – budget line 22 04]
Sector and Decision year | Programme | Allocated (million euro) | Contracted (million euro) | Paid (million euro) |
2014 | 170.00 | 163.75 | 73.26 | |
Health | Programme d'appui sectoriel à la réforme de système de santé | 90.00 | 89.73 | 47.93 |
Justice | Programme d'appui sectoriel à la réforme de la justice | 70.00 | 69.85 | 24.25 |
General budget support-related aid | Reussir le Statut Avancé (phase II) top-up Dec 2013/24-875 | 10.00 | 4.18 | 1.08 |
2015 | 175.00 | 165.60 | 69.19 | |
Health | Programme d'appui sectoriel à la réforme de système de santé II | 10.00 | 8.80 | 0.26 |
Justice | Programme d'appui à la réforme du secteur de la Justice | 5.50 | 5.50 | 0.00 |
Public sector policy | Financement additionnel 2015 au programme ''Hakama'' Gouvernance | 9.50 | 5.24 | 1.32 |
PACC | Financement additionnel n°1 (2015) au Programme Croissance Compétitivité | 5.00 | 5.00 | 5.00 |
PACC | Programme d'apppui à la croissance et la compétitivité au Maroc - PACC | 100.00 | 96.06 | 47.84 |
Vocational Training | Formation professionnelle: développement du capital humain au Maroc | 45.00 | 45.00 | 14.77 |
2016 | 150.00 | 137.51 | 33.23 | |
Public sector policy | Programme d'appui aux politiques migratoires du Maroc | 35.00 | 33.00 | 7.85 |
Social Protection | Programme d'appui à la Protection sociale au Maroc | 100.00 | 91.41 | 22.51 |
Vocational Training | Formation professionnelle: développement du capital humain au Maroc | 15.00 | 13.10 | 2.88 |
2017 | 116.20 | 45.00 | 0.00 | |
Basic life skills for youth and adults | Programme d'appui à la stratégie nationale d'alphabétisation au Maroc - 3ème phase | 50.00 | 45.00 | 0.00 |
Forestry policy | Forestry policy and administrative management Programme additionnel au PAPFM | 12.50 | 0.00 | 0.00 |
Social Protection | Multisector aid for basic social services Top up au programme d'appui à la Protection sociale | 9.20 | 0.00 | 0.00 |
Women's equality organisations and institutions | Women's equality organisations and institutions Egalité- Moussawat | 35.00 | 0.00 | 0.00 |
General budget support-related aid | Top-up au Programme Réussir le Statut Avancé phase II (RSA II) | 9.50 | 0.00 | 0.00 |
2018 | 199.20 | 50.11 | 30.00 | |
Basic life skills for youth and adults | Programme d'appui à la Jeunesse au Maroc | 35.00 | 0.00 | 0.00 |
Public sector policy | Programme d'appui aux réformes de gouvernance publique - HAKAMA 2 | 62.00 | 0.00 | 0.00 |
Justice | Top up convention justice | 2.20 | 0.11 | 0.00 |
Rural development | Programme d'Appui au Développement Territorial au Maroc (PADT) | 50.00 | 0.00 | 0.00 |
General budget support-related aid | Top up au programme ''Réussir le Statut Avancé II'' (RSA II) | 50.00 | 50.00 | 30.00 |
Total | 810.40 | 561.98 | 205.69 | |
Covered in the audit scope | 391.90 | 366.46 | 147.78 | |
48.36 % | 65.21 % | 71.85 % |
Source: European Court of Auditors.
Annex III – Funding by other EU instruments (2014-2018)
Domain of EU support (contract portfolio 2014 – 2018) | Contracted amount (euro) |
1) NIF – Neighbourhood Investment Facility | 199 966 000 |
2) EUTF – EU Trust Fund projects for Morocco | 40 800 000 |
3) EIDHR – European Instrument for Democracy and Human Rights | 4 750 288 |
4) ENI Global allocation for Morocco | 4 905 834 |
5) CSO – GENR- LA – Civil Society, Gender and Local authorities | 3 732 747 |
6) HUM – Human development | 1 586 000 |
Total | 255 740 869 |
Source: European Commission.
Annex IV – Overview of contracts/projects audited
Sector | Type | Contract title | Committed amount million € |
Paid amount million € |
Health | BS | Contrat pour le versement des différentes tranches de l'appui budgétaire du programme PASS II | 94.00 | 46.57 |
Health | Project | Assistance Technique pour l'accompagnement du programme d'Appui à la réforme du secteur de la santé-Phase II (PASS II) | 3.30 | 1.15 |
Health | Project | Projet d’appui à la réforme des Soins de Santé Primaires-Contrat PAGODA UE/OMS | 0.80 | 0.16 |
Health | Project | Appui au développement des capacités de l'Ecole Nationale de Santé Publique (ENSP) pour un meilleur accompagnement des réformes de santé et des gestionnaires des structures de soins. | 0.03 | 0.01 |
Health - Total | 98.13 | 47.89 | ||
Social Protection | BS | Contrat pour le versement des 4 tranches de l'appui budgétaire du programme d'appui à la Protection Sociale | 90.00 | 22.00 |
Social Protection | Project | Contrat PAGODA UE/UNICEF - Programme d'appui à une protection sociale intégrée et sensible aux enfants au Maroc | 1.10 | 0.44 |
Social Protection - Total | 91.10 | 22.44 | ||
Justice | BS | Contrat pour le versement des différentes tranches de l'appui budgétaire du programme Justice | 65.50 | 19.60 |
Justice | Project | Assistance technique pour le programme d'appui sectoriel à la réforme de la justice au Maroc | 3.29 | 0.64 |
Justice | Project | Accès des enfants à une justice adaptée et respectueuse de leurs droits - projet UNICEF | 2.80 | 1.74 |
Justice | Project | Amélioration du fonctionnement de la justice au Maroc sur la base des outils dévelopés par la Commission européenne pour l’efficacité de la justice (CEPEJ)” | 1.60 | 1.58 |
Justice | Project | Appui pour la réforme institutionnelle et le renforcement des capacités de l’Institut Supérieur de la Magistrature | 1.20 | 0.59 |
Justice - Total | 74.39 | 24.14 | ||
PACC | BS | Contrat d'appui budgétaire pour l'appui à la croissance verte et à la compétitivité du Maroc. | 99.00 | 51.80 |
PACC | Project | Subvention à la GIZ pour l'opérationnalisation de la stratégie des Très Petites, Petites et Moyennes entreprises au Maroc | 1.80 | 0.88 |
PACC | Project | Organisation du séminaire EIP (European External Plan of Investment) au Maroc | 0.02 | 0.02 |
PACC - TOTAL | 100.82 | 52.70 |
Source: ABAC.
Annex V – Budget support programme objectives
BS Sector | Overall objective | Specific Objectives |
Health | Increase equal access to qualitative healthcare. |
|
Social Protection | Contribute to reducing inequality, improving social cohesion and tangibly improving human development in Moroccan society by promoting equal access to social and basic services. |
|
Justice | Reinforce the rule of law through an accessible, independent judicial system that meets international standards. |
|
PACC | Support the competitiveness and growth of Morocco, with the ultimate aim of supporting the country in its ambition of sustainable development and the creation of decent jobs. |
|
Source: European Commission.
Annex VI – Variable tranche disbursement issues
Sector | Tranche | Indicator | Issue | Facts | Financial Impact (incorrectly paid)* | Regular payment. However, not contributing to the budget support programme objective | Weak control procedures |
Health | 1st variable | I.1 Number of contacts of curative medical consultations by the rural primary health care system per capita per year | Overestimation of result due to inappropriate calculation method Payment for 'results', although the situation worsened Outdated baseline |
Baseline (2012): 36 ; (2014) 38 - Target (2015): 40 - Achievement: 37 (1) Outdated baseline, as data from 2012 were used. (2) Inappropriate calculation method. Progress should be measured (37-36) / (40-36)=25 %. NB.: With the method of the EC (37/40=93 %), "progress" would be paid even if the baseline stays the same. (36/40=90 %). (3) Performance: The balance is declining since the BS started |
2,394,000 € | ||
Health | 1st variable | I.11 Number of general practitioners in post in the primary health centers "ESSP" in rural areas |
Payment for 'results', although the situation worsened Overestimation of result due to inappropriate calculation method |
Baseline: 1066 - Target: 1300 - Achievement: 1057 (1) There is no progress, the balance is declining. (2) Inappropriate calculation method by the Commission (1057/1300=81 % of progress) |
1,197,000 € | ||
Health | 1st variable | I.7 Number of diabetic patients monitored in public health facilities in rural areas | Overestimation of result due to inappropriate calculation method No impact on the specific objective |
Baseline: 183 962 (2013) - Target: 225 000 - Achievement: 215 464 (1) The progress (2015) is overestimated by EC using an inappropriate calculation method: (215.464/225.000)=96% leading to a 100% paiment. However, the progress is at best (215094-183 962)/(225 000-183 962)=77%. This should have led to a 50% paiment only. (Starting point of measuring progres is the baseline) (2) Using the updated baseline (2014) the real progress is in reality only: (215 464 - 191 250) / (225 000 - 191 250)=71 % (Leading to the same result: a 50 % payment) (3) The objective was to improve the urban/rural disparity. However, the indicator does not measure this and in addition there is no progress towards this objective. The expert report states: "The proportion .. (urban and rural)...remained stable". |
1,197,000 € | 1,197,000 € | |
Health | 2nd variable | I.7 Number of diabetic patients monitored in public health facilities in rural areas | No impact on the specific objective | Target: 235 000 - Achievement: 235 094 The specific objective was to improve the urban/rural disparity. However, the indicator does not measure this and there is no progress towards this objective. The situation worsened despite a nominal increase in figures. The expert report states: "The majority of this increase stems from the urban area...". |
3,291,667 € | ||
Health | 1st variable | I.8 Number of hypertensive patients in public health facilities in rural areas | No impact on the specific objective | Target: 300.000 - Achievement: 328.579 The objective was to improve the urban/rural disparity . However, the indicator does not measure this and there is no progress towards this objective. The situation worsened (despite a nominal increase in figures). The expert report states: "..the relative proportion of the rural area shows a small decrease .." |
2,394,000 € | ||
Health | 2nd variable | I.8 Number of hypertensive patients in public health facilities in rural areas | No impact on the specific objective | Target: 250.000 - Achievement: 281.677 The objective was to improve the urban/rural disparity. However, the indicator does not measure this and there is no progress towards this objective. The situation worsened (despite a nominal increase in figures). The expert report states: "The increase observed in 2016 stems for 56,6% out of the urban area..." |
3,291,667 € | ||
Health | 2nd variable | I.6 Availability of essential drugs in public primary health structures (ESSPs) | No baseline Payment for 'results', although the situation worsened |
Declining balance since start of the programme: Wheras availability was 82.71 % in 2016, for 2017 it is 79.71 %. | 1,645,833 € | ||
Health | 1st variable | I.9 Existence and implementation of a national health plan for the disabled | Already achieved before signing the financing agreement Outdated baseline |
The plan was published in October 2015, after a consultation process starting already back in 2014. The BS was signed in November 2015. | 2,394,000 € | ||
Health | 1st variable | I.3 Proportion of births (assisted by qualified personnel) in rural areas in public health structures | Outdated baseline Payment for 'results', although the situation worsened |
Baseline (2012): 71 %; (2014): 86 % - Target (2015): 75 % - Achievement: 85.6 % No real progress: Declining balance in 2015 compared to 2014 (outdated baseline/target) |
2,394,000 € | ||
Health | 2nd variable | I.3 Proportion of births (assisted by qualified personnel) in rural areas in public health structures | Outdated baseline Payment for 'results', although the situation worsened |
Baseline (2012): 71 %; (2014): 86 % - Target (2015): 75 %; (2016) - Achievement (2015): 85.6 %; (2016): 85 % No real progress: declining balance since BS start. |
3,291,667 € | ||
4,788,000 € | 19,899,834 € | ||||||
Sector | Tranche | Indicator | Issue | Facts | Financial Impact (incorrectly paid) | Regular payment. However, not contributing to the budget support programme objective | Weak control procedures |
Social Protection | 1st variable | 1.2. There is a three year budget programming for the social sectors | Not achieved / Inappropriate source of verification | A three-year budgetary plan for the social services sector was required for the period 2017-2020 in order for the indicator to be achieved, but the EU Delegation was satisfied with ‘sufficient progress in investments in the social sector’. The EU Delegation based its opinion on historical figures of 2017 and 2018 and the forecast of 2019.The Ministry of Economy and Finance acknowledged that no such plan was in place. Furthermore, the ministry requested technical assistance, as it did not have the necessary expertise in place to develop this type of three-year budgetary plan for the social sector. | 2,000,000 € | ||
Social Protection | 1st variable | 2.4. Global medical coverage of the population | Inappropriate source of verification / Contradiction with other sources of verification (achievement cannot be guaranteed) | The ANAM provided an Excel table with data by population category of people insured. The data could not be traced back to their annual report, nor did the EU Delegation crosscheck the data with other sources. In addition, the 2017 data was compared to the 2014 population (which was lower than the 2017 population) to calculate coverage of the Moroccan population. According to reports by the National Statistics Office and ‘Office National du Développement Humain’, the total medical coverage was only 46.6 % and 53.8 % respectively in 2017, which is even lower than the baseline situation. The data of ANAM was based on cards distributed (RAMED), and the results of the National Statistics Office given orally by the sample of households when asked whether they had a RAMED card. Another study of the National Statistics Office found that only 30 % of cardholders had the actual right to have a RAMED card. The other cardholders had sufficient income to cover a regular medical insurance. As such, the ANAM figurescannot really be considered reliable. |
2,000,000 € | ||
2,000,000 € | 2,000,000 € | ||||||
Justice | 1st variable | 3: Rationalisation of the judicial map | Not achieved/Inappropriate source of verification | Target b of indicator 3 was not achieved. A total of 72 judicial centres were supposed to be operational by end of 2017. 64 had already been active before and 8 judicial centers had to be activated. Only 1 out of those 8 was activated (Tarfaya) by December 2018, i.e. one year after the disbursement was decided. | 800,000 € | ||
Justice | 1st variable | 4: Availability of judicial assistance | Not achieved/Inappropriate source of verification | The source of verification used (RAMED) is not an appropriate means to measure the achievement of this indicator and was not provided as source of verification in the financing agreement. In addition, the RAMED card cannot be considered as a reliable source, given the focus on the improvement of its reliability in the budget support programme on social protection. | 1,280,000 € | ||
Justice | 1st variable | 9: Digitalisation of the jurisdictions | Inappropriate source of verification | The verification source "annual report of the Ministry of Justice" was not provided. A verification mission was carried out in January 2018, whereas the payment already took place in December 2017. | 1,600,000 € | ||
3,680,000 € | |||||||
Sector | Tranche | Indicator | Issue | Facts | Financial Impact (incorrectly paid) | Regular payment. However, not contributing to the budget support programme objective | Weak control procedures |
PACC | 1st variable | T1D1: Number of registered auto-entrepreneurs and cardholders | Inappropriate source of verification | The number of auto-entrepreneurs (indicators T1D1 to T1D4) is based on reports by Maroc PME. The database is managed by Maroc Poste; no checks were carried out by the EU Delegation or the experts to check the accuracy of the information. The number of cardholders does not guarantee that these people actually have a formal activity as auto-entrepreneurs. A sample of ‘auto-entrepreneurs’ tested during our visit to Morocco confirmed that the database was not accurate. In addition, there is a significant discrepancy between the number of cardholders and those declaring taxes. | 2,400,000 € | ||
PACC | 1st variable | T1D3: Two feasibility studies for industrial parks | Inappropriate source of verification / Not achieved | Studies were launched for economic activity zones and not for integrated industrial parks, as provided for in the industrial acceleration plan. | 2,400,000 € | ||
PACC | 1st variable | T1D6: Evaluation of the national plan of the simplification of procedures | Not achieved | The evaluation was not presented in due time (only 1 year later). Consequently, T1D5 could not be verified either. | 2,400,000 € | ||
PACC | 2nd variable | T2D1: Number of registered auto-entrepreneurs and cardholders | Inappropriate source of verification | See T1D1 | 2,400,000 € | ||
9,600,000 € | |||||||
6,788,000 € | 19,899,834 € | 15,280,000 € |
* On 31st May 2019, the Commission informed the Ministry of Economy and Finance that the amounts related to indicators one and eleven are going to be offset against the payment of the next variable tranche.
Source: European Court of Auditors.
Annex VII – Evolution of key indicators
Source: European Court of Auditors.
Annex VIII – Budget support contract ratings by sector
Sector | Health | Social Protection | Justice | PACC | ||
Contract duration, months | 60 | 60 | 60 (extended to 84) | 60 (extended to 72) | ||
Contract year | 2014 | 2017 | 2015 | 2016 | ||
Audit Question 1. Did the Commission and the EEAS appropriately manage EU support to Morocco? | 1.1. Did the Commission and the EEAS identify priority sectors and allocate funding accordingly? | There is complementarity with other EU support in the country | ||||
1.2. Did the Commission design programmes/projects well? | Budget support conditions are in line with the EU Action Plan for Morocco | |||||
Budget support conditions are designed to effectively support reforms | ||||||
EU actions contribute to sector needs | ||||||
EU actions are designed in a way that objective performance monitoring is ensured | ||||||
Design of the programmes takes into account lessons learnt from previous budget support programmes | No previous programme | No previous programme | ||||
1.3. Were the programmes/projects coordinated well with other actors? | The programming, allocation of funding and implementation of programmes is well coordinated with other donors | |||||
Donor coordination arrangements are established. Information is exchanged with other donors on a regular basis. | ||||||
1.4. Did the Commission monitor and evaluate the programmes/projects well? | Implementation takes place according to planning (timing, budget, activities). Deviations are well justified. Corrective action was taken if necessary. | |||||
Budget support conditions were respected. | ||||||
(Sector) policy dialogue was held regularly, relevant and discussed the programmes and conditions in sufficient detail. | ||||||
The Commission regularly carries out field visits and evaluations. They are documented and recommendations made are followed up. | ||||||
Audit Question 2. Were the objectives of the EU support to Morocco achieved? | 2.1. Were the planned results achieved? | Planned outputs have been achieved. | ongoing, but delayed | ongoing | ongoing, but delayed | ongoing, but delayed |
Disbursements were based on the achievement of the targets set for the indicators, which was supported by reliable and relevant audit evidence | ||||||
The technical assistance provided is sufficient, timely and well targeted and it assists the framework of the policy dialogue | ||||||
Budget support supported the expected reforms in sector policy formulation and/or implementation processes | ||||||
2.2. Did the Commission effectively take into account cross-cutting issues (gender and human rights) when delivering support to Morocco? | Budget support contributed to adherence to cross-cutting issues (gender and human rights) | |||||
Gender and human rights were addressed in the (sectoral) policy dialogue |
Legend - The following ratings have been established:
Criterion met | |
Crtierion partially met | |
Criterion not met |
Source: European Court of Auditors.
Acronyms and abbreviations
ADB: African Development Bank
BS: Budget Support
CJEU: Court of Justice of the European Union
EEAS: European External Action Service
ENI: European Neighbourhood Instrument
ENP: European Neighbourhood Policy
EU: European Union
PACC: Programme d’appui à la croissance verte et la compétitivité du Maroc
SME: Small- and Medium-sized Enterprise
SSF: Single Support Framework
WB: World Bank
Audit team
The ECA’s special reports set out the results of its audits of EU policies and programmes, or of management-related topics from specific budgetary areas. The ECA selects and designs these audit tasks to maximise impact by considering the risks to performance or compliance, the level of income or spending involved, forthcoming developments and political and public interest.
This performance audit was carried out by Audit Chamber III, External actions/Security and justice, headed by ECA Member
Endnotes
1 Source: Commission figures for 2017 (DG Trade).
2 United Nations Human Rights Council – Universal Periodic Review Morocco May 2017.
3 "Euro-Mediterranean Agreement establishing an association between the European Communities and their Member States, of the one part, and the Kingdom of Morocco, of the other part" – OJ L 70, 18.3.2000, p. 2.
4 Document conjoint UE-Maroc sur le renforcement des relations bilatérales/ Statut Avancé (13653/08).
5 Judgment by the General Court of the EU of 10 December 2015 (Case T-512/12).
6 2012/497/EU: Council Decision, (OJ L 241, 7.9.2012, p. 2).
7 Judgment by the CJEU of 21 December 2016 (Case C-104/16 P).
8 Judgment of the CJEU of 27 February 2018 (Case C-266/16).
9 65 % of allocated expenditure and 72 % of payments.
10 Single Support Framework 2014-2017. The sub-sectors include for example health, education, justice and rural development.
11 Increasing the impact of EU Development Policy: an Agenda for Change (COM(2011) 637 final).
12 The indicative allocations provided for in the SSF, the level of funding at which the EU can ensure sufficient policy leverage, additional funding required for strategy implementation, absorption capacity and other stakeholder interventions.
13 Meeting between the Moroccan authorities led by the Minister of Foreign Affairs, the EU High Representative for Common Foreign Security and Policy, the EU Commissioner for European Neighbourhood Policy and enlargement negotiations and the Member States’ representatives.
14 Of the 54 targets considered for disbursement, 24 should have had an appropriate baseline. However, a baseline was set for only seven targets. Eight targets had an inaccurate baseline or none at all, and nine targets had an outdated baseline.
15 Of the 24 targets that should have had a baseline, nine had an outdated baseline. Of the 54 targets considered for disbursement, eight had already been achieved before the financing agreement was signed.
16 The design phase is time-consuming (about a year) and is subject to various levels of approval. The Commission does not have the flexibility to change the targets or indicators at the end of the negotiation procedure.
18 Twelve out of the 42 targets for which this was applicable (i.e. 29%).
19 A target can belong to one or more of the following sub-headings.
20 Which included the creation of a Court of Appeal in Guelmim and 13 Courts of First Instance (through the creation of a Court of First Instance in Tahenaout and the transformation of 12 judicial centres into Courts of First Instance, including Sidi Ifni).
21 According to the expert mission report (November 2017) approved by the European Commission, this implementation rate of 60 % results from the reduction of the number of judicial centres from 120 to 72 (eight of which had to be activated) as provided by a ministerial decision.
22 European Commission - Issues Paper: a review of the budget support instrument in Morocco, March 2015 and October 2018.
23 National programme for learning support.
24 National programme for direct support to widows with children.
25 Freedom House is a non-governmental organisation that conducts research and provides advocacy regarding democracy, political freedom and human rights.
26 E.g., https://freedomhouse.org/report/freedom-world/2018/morocco.
27 International Commission of Jurists, ‘Reform the criminal justice system in Morocco: strengthen pre-trial rights, guarantees and procedures’ (April 2017).
28 It is one of the Moroccan Government’s major strategies aimed at (i) increasing the number of jobs in the industrial sector, (ii) changing the structure of the Moroccan economy by increasing the share of industry in the GDP, (iii) increasing exports of industrial products, (iv) increasing foreign direct investments in industry and (v) improving the productivity of the sector.
29 Based on a survey by the General Confederation of Companies in Morocco in 2014.
30 All individuals whose consumption expenditure is below the national poverty line ($2.15 per day) are considered poor (World Bank country diagnostics June 2018).
31 The Gini coefficient is used to measure income distribution across percentiles in a population. The higher the Gini coefficient, the greater the country’s inequality, with high-income individuals receiving much larger percentages of the total income of the population than the average percentage per capita.
32 African Development Dynamics 2018 (11 July 2018).
33 A composite index reflecting inequality between women and men in three dimensions of achievement: reproductive health, empowerment and the labour market; 100 % = inequality and 0 % = equality.
34 A composite index measuring average achievement in three basic dimensions of human development — a long and healthy life, knowledge and a decent standard of living.
Timeline
Event | Date |
---|---|
Adoption of Audit Planning Memorandum (APM) / Start of audit | 25.9.2018 |
Official sending of draft report to Commission (or other auditee) | 3.6.2019 |
Adoption of the final report after the adversarial procedure | 14.11.2019 |
Official replies of the Commission and the EEAS received in all languages | 5.12.2019 |
Contact
EUROPEAN COURT OF AUDITORS
12, rue Alcide De Gasperi
1615 Luxembourg
LUXEMBOURG
Tel. +352 4398-1
Enquiries: eca.europa.eu/en/Pages/ContactForm.aspx
Website: eca.europa.eu
Twitter: @EUAuditors
More information on the European Union is available on the internet (http://europa.eu).
Luxembourg: Publications Office of the European Union, 2019
ISBN 978-92-847-4012-3 | ISSN 1977-5679 | doi:10.2865/749032 | QJ-AB-19-022-EN-N | |
HTML | ISBN 978-92-847-4016-1 | ISSN 1977-5679 | doi:10.2865/314136 | QJ-AB-19-022-EN-Q |
© European Union, 2019.
Reuse is authorised provided the source is acknowledged.
For any use or reproduction of photos or other material that is not under the copyright of the European Union, permission must be sought directly from the copyright holders.
GETTING IN TOUCH WITH THE EU
In person
All over the European Union there are hundreds of Europe Direct Information Centres. You can find the address of the centre nearest you at: https://europa.eu/european-union/contact_en
On the phone or by e-mail
Europe Direct is a service that your questions about the European Union. You can contact this service
- by freephone: 00 800 6 7 8 9 10 11 (certain operators may charge for these calls),
- at the following standard number: +32 22999696 or
- by electronic mail via: https://europa.eu/european-union/contact_en
FINDING INFORMATION ABOUT THE EU
Online
Information about the European Union in all the official languages of the EU is available on the Europa website at: https://europa.eu/european-union/index_en
EU Publications
You can download or order free and priced EU publications at: https://op.europa.eu/en/web/general-publications/publications. Multiple copies of free publications may be obtained by contacting Europe Direct or your local information centre (see https://europa.eu/european-union/contact_en)
EU law and related documents
For access to legal information from the EU, including all EU law since 1952 in all the official language versions, go to EUR-Lex at: http://eur-lex.europa.eu/homepage.html?locale=en
Open data from the EU
The EU Open Data Portal (http://data.europa.eu/euodp/en/data) provides access to datasets from the EU. Data can be downloaded and reused for free, both for commercial and non-commercial purposes.