The contract is for the engagement of a project coordinator for clearing environmental toxins in sediments in Bergen harbour.
The following activities are planned for the period 2013-2014:
— Working out a detailed initiative plan for Vågen.
— Engineering design services for and working out the tender documents for the initiative.
— Carry out mapping and implementation of initiatives on prioritised land sources.
— Follow up of initiatives in Kirkebukten as regards the measurement of the effect of the implemented cover.
— Update the risk assessment and initiative plan for Puddefjorden and Store Lungegårdsvann.
The project coordinator is professionally and administratively responsible for the execution, follow up and coordination of the planned activities in the project.
NOTE: To register your interest in this notice and obtain any additional information please visit the Doffin Web Site at http://www.doffin.no/Search/Search_Switch.aspx?ID=292692
Pamatnolīgums ar single operators
Šajā lapā publicētā informācija ir tikai papildu informācijas avots, un tai nav juridiska spēka. Eiropas Savienības iestādes neatbild par tās saturu. Attiecīgo līguma paziņojumu oficiālās versijas ir tās, kas publicētas Eiropas Savienības Oficiālā Vēstneša papildinājumā un pieejamas vietnē TED. Šie oficiāli spēkā esošie dokumenti ir tieši pieejami, noklikšķinot uz šajā lapā iegultajām saitēm. Sīkāku informāciju skatiet paziņojumā par izskaidrojamību un atbildību publiskā iepirkuma jomā.