Foilsithe23/11/2016
-
Sprioc‑am16/12/2016
-
Inniu08/09/2026
Áirgiúlachtaí
Ríocht Aontaithe, an-Birmingham: Electricity
Against a backdrop of increasing energy costs, the need to ensure that the Airport is resilient in terms of meeting challenges associated with the potential supply shortages arising from national infrastructure and the desire to satisfy environmental criteria with regard to energy supply from more environmentally friendly sources; the Airport is seeking to enter into a long term arrangement (up to 25 years) for the supply of energy.
The energy demands of the Airport are 41 GWh p.a.in respect of power and 7.7 GWh p.a.in respect of heat and the Airport has an objective to have all of this demand met under the new supply arrangements before the end of 2018.
In order to provide additional resilience, the Airport will require grid connection arrangements to be put in place under the scope of this project.
It should be noted that the Airport has constraints regarding the availability of land and as such has no on-site land available for a solution to deliver the power requirement, but does have a small site at the Airport available for a solution to deliver the heat requirement.
This contract is split into Lots as follows:
Lot 1 — Heat and Power;
Lot 2 — Heat only;
Lot 3 — Power only.
Expressions of interest for any combination of these Lots is permitted.
An t-ábhar seo a fhoilsítear ar an leathanach seo, is mar sheirbhís bhreise amháin atá sé beartaithe agus níl aon éifeacht dhlíthiúil aige. Ní ghabhann institiúidí an Aontais aon dliteanas orthu féin i leith inneachar an téacs. Is iad na leaganacha oifigiúla de na fógraí tairisceana ábhartha na cinn a fhoilsítear i bhForlíonadh Iris Oifigiúil an Aontais Eorpaigh agus atá ar fáil in TED. Is féidir teacht ar na téacsanna oifigiúla sin ach na naisc atá leabaithe sa leathanach seo a bhrú. Chun tuilleadh eolais a fháil, féach an fógra maidir le Inmhínitheacht agus Dilteanas Soláthair Phoiblí.