Suomija-Naantali: Katilų įranga
TSE Oy owned Naantali Power Plant Unit no. 3 will be equipped with Nitrogen oxides reduction (deNOx) system to reduce nitrogen oxides emissions from present level of ≤600 mg/Nm3 to ≤180 mg/Nm3 (calculated as NO2, dry gases at normal conditions, at 6 % oxygen).
It is preliminarily assumed that the deNOx system will be based on Selective Catalytic Reduction (SCR) technology but also other technologies are accepted, if they fulfill the requirements specified in the RfQ.
The delivery shall be EPC-type including SCR-reactor with associated ducting, reagent unloading, storage and supply station and reagent evaporation, dilution and injection, and also including replacement of existing ID-fans.
The boiler of unit no 3 is Sulzer type pulverized coal fired boiler with 315 MW thermal power calculated as fuel input and flue gas flow of 140 Nm3/s.
If you are interested to participate to tendering, please leave your application by 31.10.2013 at 12:00 Finnish time to ilari.ekman@siriusengineers.com
In the application please inform the following:
1. Participating company's official name and ID number
2. Main references according to III.2.3)
3. Contact information (contact person and e-mail address) where to deliver the offer request.
4. Balance sheet according to III.2.2)
RfQ will be delivered to accepted applicants during November 2013.
Preliminary project schedule:
— Contract signed: 1.4.2014
— Take-over of the delivery: 30.9.2015
Šiame puslapyje skelbiamas turinys yra tik papildoma paslauga ir neturi teisinės galios. Europos Sąjungos institucijos nėra teisiškai atsakingos už jo turinį. Oficialios atitinkamų skelbimų apie pirkimą versijos yra paskelbtos Europos Sąjungos oficialiojo leidinio priede ir pateiktos TED. Oficialūs tekstai tiesiogiai prieinami naudojantis šiame puslapyje pateikiamomis nuorodomis. Daugiau informacijos rasite pranešime dėl viešųjų pirkimų paaiškinamumo ir atsakomybės.