Pubblicato03/05/2013
-
Termine03/06/2013
-
Oggi27/09/2026
Utilità
NO-Bergen: Servizi di consulenza per la fornitura di acqua e lo smaltimento dei rifiuti
The contract is for the engagement of a project coordinator for clearing environmental toxins in sediments in Bergen harbour.
The following activities are planned for the period 2013-2014:
— Working out a detailed initiative plan for Vågen.
— Engineering design services for and working out the tender documents for the initiative.
— Carry out mapping and implementation of initiatives on prioritised land sources.
— Follow up of initiatives in Kirkebukten as regards the measurement of the effect of the implemented cover.
— Update the risk assessment and initiative plan for Puddefjorden and Store Lungegårdsvann.
The project coordinator is professionally and administratively responsible for the execution, follow up and coordination of the planned activities in the project.
NOTE: To register your interest in this notice and obtain any additional information please visit the Doffin Web Site at http://www.doffin.no/Search/Search_Switch.aspx?ID=292692
Accordo quadro con single operatore
I contenuti pubblicati su questa pagina intendono essere un servizio aggiuntivo e non producono alcun effetto giuridico. Le istituzioni dell'Unione declinano ogni responsabilità per tali contenuti. Le versioni ufficiali dei relativi bandi o avvisi di gara sono quelle pubblicate nel supplemento della Gazzetta ufficiale dell'Unione europea e disponibili in TED. I testi ufficiali sono direttamente accessibili dai link inseriti in questa pagina. Per maggiori informazioni, consultare l'informativa sulla spiegabilità e la responsabilità negli appalti pubblici.