DK-Gentofte: Машини и устройства за филтрация или пречистване на газове

  • Objavljeno
    11/10/2011
  • Rok
    31/10/2011
  • Dodijeljeno
    09/02/2012
  • Danas
    07/10/2026
Status
Dodijeljeno
Vrsta ugovora
Supplies
Produljeni postupak
No
Kupac
Nije dostupno
Mjesto izvršenja
NUTS code: DK042 Østjylland
Lokacija kupca
NUTS code: Nije dostupno
Poslovni sektor (glavni CPV)
42514000 Strojevi i aparati za filtriranje ili pročišćavanje plinova
Ukupna procijenjena vrijednost ugovora (bez PDV-a)
Nije dostupno
Ukupna konačna vrijednost ugovora (bez PDV-a)
Nije dostupno
Referentni broj ponude
2-00381
Opis

The main data of the existing plant are as follows:
1. Flue gas amount: 71,5 kg/s;
2. Gas turbine, model GE LM250PE;
3. Degasification type: Aalborg Ciserv A/S LV24;
4. Current NOx level, both with and without water injection:
a) Without water injection: 1 100 mg/Nm3;
b) With water injection: 680 mg/Nm3.
The new SCR (selective catalytic reduction) plant must comply with the following requirements:
5. The following emissions must as a minimum be observed after installation and commissioning. When determining the level of NOx emission, all NOx must be converted into NO2. In practise, the emission of NO and NOx is measured in ppm. The found values must be added up and the sum must be converted into mg/normal m3 NO2 by the use of the conversion factor for NO2.
— The NOx emission must be kept under 150mg/Nm3 (reference state: 5 % 02, 0 degrees Celsius, 101.3 kPa, dry gas under all operational conditions,
— The ammonia emission must be kept under 12mg/Nm3 (reference state: 5 % 02, 0 degrees Celsius, 101.3 kPa, dry gas under all operational conditions.
The following is included in the supply:
— The existing ammonia storage must be used (24 % dissolution, (NH3) in connection with the installation of the plant,
— Pipe routing, pumps and electrical installation as regards connection to existing ammonia storage,
— Assembly and installation in the time frame (May 2012, June 2012, July 2012),
— Commissioning in the time frame (August 2012). Must be able to comply with emission requirements as of 1.9.2012,
— Scaffolding, insulation in connection with assembly and installation,
— Commissioning,
— Documentation Electronic + 2 x hard copy,
— Operational description (maintenance manuals) electronic + 2 x hard copy,
— C&I concept for control system (Siemens T-3000),
— Third party control and verification of emissions in connection with commissioning,
— KKS numbering of drawings, components, pipe routing and cables.

Način podnošenja
Nije dostupno
Ponude se mogu podnositi
Submission for all lots
Podaci o ugovoru o javnoj nabavi, okvirnom sporazumu ili dinamičkom sustavu nabave (DPS)
Obavijest uključuje ugovor o javnoj nabavi
Uvjeti za otvaranje ponuda (datum)
Nije dostupno
Mjesto izvršenja
Metoda dodjele
The most economic tender
Procijenjena vrijednost
Nije dostupno
Konačna ugovorena vrijednost
Nije dostupno
Dodjela ugovora
Službeno ime: Industrivarme
Poštanska adresa: Landholmvej 12
Mjesto: Storvorde
Poštanski broj: 9280
Zemlja: DNK
Prethodna informacija
Ugovor
Dodjela
Footnote - legal notice

Sadržaj objavljen na ovoj stranici smatra se isključivo dodatnom uslugom i nema pravni učinak. Institucije Unije ne preuzimaju odgovornost za njezin sadržaj. Službene verzije obavijesti o nadmetanju objavljene su u Dodatku Službenom listu Europske unije i dostupne su na TED-u. Tim službenim tekstovima može se izravno pristupiti putem poveznica na ovoj stranici. Za više informacija vidjeti Obavijest o objašnjivosti i odgovornosti u vezi s javnom nabavom.