Publications Office of the EU
DK-Gentofte: Maquinaria y aparatos de filtrado o purificación de gases - Convocatorias de concursos de la UE
DisplayCustomHeader
Procurement Detail Actions Portlet
OP Portal - Procurement - Details

DK-Gentofte: Maquinaria y aparatos de filtrado o purificación de gases

  • Publicado
    11/10/2011
  • Fecha límite
    31/10/2011
  • Concedido(s)
    09/02/2012
  • Hoy
    10/06/2026
Estado
Concedido(s)
Tipo de contrato
Supplies
Procedimiento renovado
No
Comprador
No disponible
Lugar de ejecución
NUTS code: DK042 Østjylland
Dirección del comprador
NUTS code: No disponible
Sector comercial (CPV principal)
42514000 Maquinaria y aparatos de filtrado o purificación de gases
Valor total estimado del contrato (excluido el IVA)
No disponible
Valor total final del contrato (excluido el IVA)
No disponible
Número de referencia de la oferta
2-00381
Descripción

The main data of the existing plant are as follows:
1. Flue gas amount: 71,5 kg/s;
2. Gas turbine, model GE LM250PE;
3. Degasification type: Aalborg Ciserv A/S LV24;
4. Current NOx level, both with and without water injection:
a) Without water injection: 1 100 mg/Nm3;
b) With water injection: 680 mg/Nm3.
The new SCR (selective catalytic reduction) plant must comply with the following requirements:
5. The following emissions must as a minimum be observed after installation and commissioning. When determining the level of NOx emission, all NOx must be converted into NO2. In practise, the emission of NO and NOx is measured in ppm. The found values must be added up and the sum must be converted into mg/normal m3 NO2 by the use of the conversion factor for NO2.
— The NOx emission must be kept under 150mg/Nm3 (reference state: 5 % 02, 0 degrees Celsius, 101.3 kPa, dry gas under all operational conditions,
— The ammonia emission must be kept under 12mg/Nm3 (reference state: 5 % 02, 0 degrees Celsius, 101.3 kPa, dry gas under all operational conditions.
The following is included in the supply:
— The existing ammonia storage must be used (24 % dissolution, (NH3) in connection with the installation of the plant,
— Pipe routing, pumps and electrical installation as regards connection to existing ammonia storage,
— Assembly and installation in the time frame (May 2012, June 2012, July 2012),
— Commissioning in the time frame (August 2012). Must be able to comply with emission requirements as of 1.9.2012,
— Scaffolding, insulation in connection with assembly and installation,
— Commissioning,
— Documentation Electronic + 2 x hard copy,
— Operational description (maintenance manuals) electronic + 2 x hard copy,
— C&I concept for control system (Siemens T-3000),
— Third party control and verification of emissions in connection with commissioning,
— KKS numbering of drawings, components, pipe routing and cables.

Método de presentación
No disponible
Pueden presentarse ofertas
Submission for all lots
Información sobre un contrato público, un acuerdo marco o un sistema dinámico de adquisición
El anuncio se refiere a un contrato público
Condiciones de apertura de ofertas (fecha)
No disponible
Lugar de ejecución
Método de adjudicación
The most economic tender
Valor estimado
No disponible
Valor final contratado
No disponible
Adjudicación del contrato
Denominación oficial: Industrivarme
Dirección postal: Landholmvej 12
Población/ciudad: Storvorde
Código postal: 9280
País: DNK
Información previa
Contrato
Adjudicación
Footnote - legal notice

El contenido de esta página constituye exclusivamente un servicio adicional, y no tiene efectos jurídicos. Las instituciones de la UE no asumen responsabilidad alguna por su contenido. Las versiones oficiales de los anuncios de licitación pertinentes son aquellas publicadas en el suplemento del Diario Oficial de la Unión Europea y disponibles en TED. Se puede acceder a esos textos oficiales directamente mediante los enlaces integrados en esta página. Para más información, véase la declaración relativa a la explicabilidad y la responsabilidad en materia de contratación pública.