Design (in the field of SRK and telecommunications) and execution of works for the task entitled: ‘Section 1 – Construction works on railway line No 201 station Maksymilianowo’ under the project ‘Works on the section Maksymilianowo – Kościerzyna’
Note: Not all information for this procedure were successfully computed. Please consult linked documents for more details.
I. The subject of the Order is the execution of the following elements: The entire subject of the Order includes the execution of the following elements: 1.Execution of works in the scopes (Part A): 1) Track works 2) Platforms 3) Overhead contact line 4) Line of non-traction needs 15kV 5) Power engineering up to 1 kV 6) Drainage 7) Installations, networks and sanitary facilities 8) Road system 9) Engineering structures 10) Building structures 11) Environmental protection 12) Geotechnics 13) Dendrology 14) Reconstruction of ditches and watercourses related to the construction of engineering structures 15) Small architecture and land development 2.Development of projects along with the implementation of works in the scopes (part B): 1) Railway traffic control equipment (srk), 2) Construction and reconstruction of telecommunications networks and equipment 3. Interface option: 1) Installation of line locking devices on the Maksymilianowo – Kotomierz route 2) Installation of ERTMS/ETCS level 2 4. Implementation of works consisting in the construction of facilities for environmental protection. 5. As-built documentation. II. Detailed Description of the subject of the Order is presented in the scope of Part A: the descriptive and drawing part of the Design Documentation, Technical Specifications for the Execution and Acceptance of Construction Works (STWIORB) constituting Volume III of the SWZ and in the Measurement of Works constituting a separate Volume IV of the SWZ, as well as in the scope of Part B is presented in the PFU constituting Volume III of the SWZ. III. PROCUREMENT PERIOD: 3. PERFORMANCE PERIOD OF THE ORDER The duration of the Order: 1) Basic scope – 51 months from the date of conclusion of the contract, in accordance with § 4 of the Terms and Conditions, contained in Volume II of the FTZ, including: a) completion of all Works (subject to the point below and excluding the Interface Option), confirmed by the Ordering Party's last Final Acceptance, including providing the Ordering Party with complete as-built documentation and, providing the Ordering Party with a complete set of documents related to the certification process together with certificates issued by a notified body and a complete application to the Office of Rail Transport - 42 (forty-two) months from the date of conclusion of the Agreement, b) providing the Ordering Party with authorisations for placing in service of structural subsystems, in accordance with the Rail Transport Act - no longer than within 9 (nine) months from the date of the Ordering Party's last Final Acceptance. 2) Option for the interface – not less than 6 months, provided that the deadline for implementation indicated by the Ordering Party will not be longer than 4 years from the date of launching the Option for the interface. The Ordering Party shall have the right to run the Interface Option throughout the duration of the Works and the Works warranty period, no later than before the end of the warranty period for the scope of the Works relating to railway traffic control and ETCS equipment. IV. The Contracting Authority provides for the award of contracts referred to in Article 388(2)(c) of the Act. The scope of contracts referred to in Article 388(2)(c) of the Act and the conditions under which they will be awarded are set out in the GIP. A similar contract will be awarded directly, after prior negotiations with the Contractor, in particular as regards the terms of the contract, including price, performance date, warranty period and may cover the following areas: track industry including drainage, road industry, power industry, control and automation, environmental protection, overhead contact line, earthmoving and demolition industry, platforms, telecommunications, engineering facilities, cubature facilities, development of design documentation / replacement documentation in the scope of the above-mentioned industries along with obtaining the necessary administrative decisions, construction of platforms, underground passageways, engineering facilities, acoustic screens.
https://platformazakupowa.plk-sa.pl
https://platformazakupowa.plk-sa.pl
45234113 - Demolition of tracks
45234115 - Railway signalling works
45314310 - Installation of cable laying
45312330 - Radio aerial installation work
71322000 - Engineering design services for the construction of civil engineering works
45314300 - Installation of cable infrastructure
45200000 - Works for complete or part construction and civil engineering work
45221241 - Road tunnel construction work
45300000 - Building installation work
50000000 - Repair and maintenance services
45231400 - Construction work for electricity power lines
45234000 - Construction work for railways and cable transport systems
45234100 - Railway construction works
45330000 - Plumbing and sanitary works
Type: price
Description: Całkowita cena brutto – waga: 100 %.
Weight (percentage, exact): 100
This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.