Publications Office of the EU
‘Selection of a contractor to carry out construction supervision and to assess the compliance of investment projects for the site “Construction of a composting plant for biodegradable waste for the needs of the Shumen Regional Waste Management Agency serving the municipalities of Shumen and Novi Pazar”’ - EU tenders
DisplayCustomHeader
Procurement Detail Actions Portlet
OP Portal - Procurement - Details

This page contains content generated automatically to improve findability and accessibility

- indicates text translated automatically in your browsing language

‘Selection of a contractor to carry out construction supervision and to assess the compliance of investment projects for the site “Construction of a composting plant for biodegradable waste for the needs of the Shumen Regional Waste Management Agency serving the municipalities of Shumen and Novi Pazar”’ Text automatically translated in your browsing language Automatically translated

  • Published
    27/01/2025
  • Today
    15/02/2025
  • Deadline
    27/02/2025
  • Opening of tenders
    28/02/2025
Status
Published
Type of contract
Services
Subject for Renewal
No
Buyer
ОБЩИНА ШУМЕН
Place of performance
NUTS code: Multiple place of performance
Location of buyer
NUTS code: BG333 Шумен
Business sector (Main CPV)
71521000 Construction-site supervision services
Total estimated contract value (excluding VAT)
85,000.00 BGN
Total final contract value (excluding VAT)
Not available
Tender reference number
457212
Description

1. The subject of each of the lots in No 1 includes the following activities for the site: - Exercising construction supervision during construction until the adoption and commissioning of the construction within the mandatory scope regulated by the Spatial Planning Act and the secondary legislation on its implementation, including inspection and control of the construction products delivered and used in the construction, which ensure the implementation of the basic requirements for construction works in accordance with the requirements of the ordinance under Art. 9, para. 2, item 5 of the Technical Requirements for Products Act, as well as coordination of the construction process until the commissioning of the construction, including control of the quantities, quality and conformity of the performed construction and installation works with the contract for the implementation of the engineering of the site, as well as the other activities subject to the engineering contract; - Performing the functions of a Safety and Health Coordinator in accordance with the provisions of Regulation No 2 of 2004 on the minimum requirements for health and safety at work when carrying out construction and installation works, incl. fulfilling all the obligations of the Contracting Authority provided for in that Regulation; - Preparation of a final report on the construction in accordance with Article 168(6) of the Spatial Planning Act and Regulation No 2 of 31 July 2003 on the commissioning of construction works in the Republic of Bulgaria and minimum warranty periods for completed construction and installation works, facilities and construction sites, and an updated technical passport for the construction in accordance with Article 176a of the Spatial Planning Act and Regulation No 5 of 2006 on the technical passports of construction works; - Management of the processes of commissioning until the issuance of a Permit for use; - Liability under Art. 168, para 7 of the Spatial Development Act until the expiry of the warranty periods for the respective types of construction works. 2. The subject of Lot No 2 includes assessment of compliance with the essential requirements for construction works on all parts of the investment project, in volume and content in accordance with the Spatial Planning Act, including conformity assessment and technical control of the structural part in accordance with Article 142(10) of the Spatial Planning Act and assessment of compliance with the energy efficiency requirements of Article 169(1)(6) of the Spatial Planning Act, in accordance with Article 142(11) of the Spatial Planning Act, and preparation of a comprehensive report on the conformity assessments carried out. The Contractor shall assist the Contracting Authority in the procedure for coordination and approval of the investment project and issuance of a building permit. The detailed description of the requirements for the participants is laid down in the Technical Specifications. Text automatically translated in your browsing language Automatically translated

Submission Method
Electronic via:
https://app.eop.bg/today/457212
Tenders may be submitted
Electronic submission: required
https://app.eop.bg/today/457212
Information about a public contract, a framework agreement or a dynamic purchasing system (DPS)
Not available
Conditions for opening tenders (date)
28/02/2025 13:00
Award method
П2 „Ценово предложение за изпълнение на поръчката“ е показател с максимален брой точки 100 т.. и относителна тежест 40%
Estimated value
85,000.00 BGN
Final contracted value
Not available
Award of contract
Not available
Prior information
Contract
Award
Footnote - legal notice

This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.