‘Engineering (design, supervision, construction and supply of equipment) for the site ‘Reconstruction and modernisation of the Veliko Tarnovo WWTP’ Text automatically translated in your browsing language Automatically translated
The scope of work shall include at least the following elements: Review and analysis of the available project documentation for the planned activities, as well as its alignment with the current Bulgarian standards for design and construction, the Spatial Planning Act and the secondary legislation for its implementation; Preparation of an investment project in the working design phase for the site ‘Implementation of engineering (design, author's supervision and construction and installation works) of the site: “Reconstruction and modernization of the waste water treatment plant Veliko Tarnovo” under the contractual terms of FIDIC – Yellow Book, 1999” in accordance with Ordinance No 4 of 21 May 2001 on the scope and content of investment projects, in force since 5 June 2001, issued by the Minister of Regional Development and Public Works, Prom. SG No 51 of 5 June 2001, amended in SG No 85 of 27 October 2009, amended SG No 96 of 4 December 2009, amended and supplemented SG No 93 of 11 November 2014, amended in SG No 102 of 12 December 2014, amended in SG No 13 of 17 February 2015, amended in SG No 44 of 2 June 2017 , Spatial Planning Act, in force since 31.03.2001 and its implementing regulations; Coordination of the project with all control bodies, operating companies and institutions in accordance with the requirements of the regulatory framework; Obtaining all necessary opinions and permits according to the Bulgarian legislation; Obtaining a building permit and lawful commencement of construction; Execution of construction and installation works and any other accompanying and related activities necessary for the execution of the construction, in accordance with the regulatory requirements, the requirements of the Contracting Authority, the drawings and tables; Implementation of author's supervision under the Spatial Development Act, technical solutions, adjustments and amendments to the project, technological control and assistance in putting the site into operation; Preparation of executive documentation, cadastral surveying of the entire site and submission to the relevant office of geodesy, cartography and cadastre of data in accordance with the Cadastre and Property Register Act; Preparation of instructions for maintenance and operation of WWTP Veliko Tarnovo; Training of the staff of the Assignor, monitoring and support of the operation and maintenance of the Site; Submission of the Site and its acceptance by the Assignor, by act Model 15 under Regulation No 3 of 31 July 2003 on the drawing up of acts and protocols during construction and Certificate of Acceptance by the Engineer/Construction Supervision; Samples after completion according to process warranty; Period for reporting and correction of defects - monitoring of the processes, reaching the design parameters and assisting the personnel in the operation and maintenance of the newly built elements of the site; removal at the expense of the Contractor of defects found in the Warranty Periods. Pursuant to Article 104(2) of the Public Procurement Act, the contracting authority provides for the evaluation of the technical and price proposals of the participants to be carried out before examining the documents for compliance with the requirements for personal status and the selection criteria. Pursuant to Article 114 of the Public Procurement Act, the contract for the award of the public procurement contract will be concluded conditionally, as at the time of the opening of the procedure funding for the entire value of the public procurement is not provided. Text automatically translated in your browsing language Automatically translated
https://app.eop.bg/today/452911
https://app.eop.bg/today/452911
This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.