General renovation of the corridor (GS) Cologne – Remagen (left Rhine) Text automatically translated in your browsing language Automatically translated

  • Announced
    18/06/2025
  • Today
    11/07/2025
Status
Announced
Type of contract
Works
Subject for Renewal
No
Buyer
DB InfraGO AG – Geschäftsbereich Fahrweg (Bukr 16)
Place of performance
NUTS code: Multiple place of performance
Location of buyer
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Business sector (Main CPV)
45234100 Railway construction works
Total estimated contract value (excluding VAT)
Not available
Total final contract value (excluding VAT)
Not available
Tender reference number
25FEI81810
Description

As part of the general renovation, extensive infrastructure measures are planned on route 2630 between Hürth-Kalscheuren and Remagen. The implementation takes place mainly during a five-month total closure from 4 February to 7 July 2028. In addition, a 10-week nightly and weekend-long one-sided blocking break (ESP) from 31 July to 15 October 2027 is planned in advance. Preparatory measures are to be carried out during this period, in particular foundation work for the overhead contact line systems, underground cable construction and ordnance prospecting. As part of the project, around 56 kilometres of track will be renewed and a total of 114 new switches will be built or renewed. In addition, the superstructure of a bridge, the filling of air protection rooms, the renewal of a retaining wall and the new construction of a total of seven noise protection walls of a total length of 5.3 km will be carried out. It is also planned to renew four interlockings, including about 421 LST interlocking units. In addition, a new operating site (BSO) is planned. In addition, LST components and/or the level crossing surface are renewed at 13 level crossings. As part of the adaptation measures to the switches, around 25 kilometres of overhead contact line - including the associated supporting structures - will be renewed according to the current planning status. In addition, the overhead line in the station areas of Roisdorf, Sechtem and Brühl will be completely renewed. In addition, the contact wire is replaced on a distance of about 37 kilometers. In addition, the renewal of eight point heating systems and the installation of four hot-runner detection systems (HOA) are planned. In addition, measures are planned at seven transport stations. These include measures on eight platforms, six platform roofs, eight lifts, three passenger underpasses and numerous travel information systems. Text automatically translated in your browsing language Automatically translated

Submission Method
Not available
Tenders may be submitted
Not available
Information about a public contract, a framework agreement or a dynamic purchasing system (DPS)
The procurement involves the establishment of a framework agreement
Conditions for opening tenders (date)
Not available
Award method
Not available
Estimated value
Not available
Final contracted value
Not available
Award of contract
Not available
Prior information
Contract
Award
Footnote - legal notice

This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.