Publications Office of the EU
2024-1004343_Munich Airport_General Planning Construction 3. Electricity grid (LPH 4 to 8), primarily for the integration of consumers of e-mobility and PV systems - EU tenders
DisplayCustomHeader
Procurement Detail Actions Portlet
OP Portal - Procurement - Details

This page contains content generated automatically to improve findability and accessibility

- indicates text translated automatically in your browsing language

2024-1004343_Munich Airport_General Planning Construction 3. Electricity grid (LPH 4 to 8), primarily for the integration of consumers of e-mobility and PV systems Text automatically translated in your browsing language Automatically translated

  • Published
    26/11/2024
  • Deadline
    02/01/2025
  • Awarded
    30/04/2025
  • Today
    11/07/2025
Status
Awarded
Type of contract
Services
Subject for Renewal
No
Buyer
Flughafen München GmbH
Place of performance
NUTS code: Multiple place of performance
Location of buyer
NUTS code: DE21B Freising
Business sector (Main CPV)
71320000 Engineering design services
Total estimated contract value (excluding VAT)
Not available
Total final contract value (excluding VAT)
-1.00 EUR
Tender reference number
2024-1004343
Description

For reasons of increasing performance and ensuring network stability for regular airport operations, a new third network is to be set up at Munich Airport. This network is primarily intended to integrate consumers of electromobility and photovoltaic systems. At present, it is assumed that about 40 MW will be available for future e-mobility and that a generation with photovoltaics with a peak of about 50 MW will be carried out. The planned power size is approx. 80MVA reference. For this purpose, a new substation with two auto-transformers of 80 MVA in n-1 configuration is planned on the FMG site. Basically, the 3. Network with 1. The network is coupled. Optionally, a dynamic coupling with the 2. network is provided. Furthermore, two battery storage systems with a total gross reserve of around 200 MWh are to be integrated into the third grid. The planning services for the new 110/20 kV substation to be built, the battery storage facility(s) and the photovoltaic systems to be built are each tendered separately. The required interface engineering for the above-mentioned lots is part of the contract. Text automatically translated in your browsing language Automatically translated

Submission Method
Electronic via:
https://www.dtvp.de/Satellite/notice/CXP4Y9D5RCK
Tenders may be submitted
Electronic submission: required
https://www.dtvp.de/Satellite/notice/CXP4Y9D5RCK
Information about a public contract, a framework agreement or a dynamic purchasing system (DPS)
Not available
Conditions for opening tenders (date)
Not available
Place of performance
Award method
Preis
Estimated value
Not available
Final contracted value
-1.00 EUR
Award of contract
Official name: Planungsgemeinschaft act-technik/act-consult/Richter Ing. Ges. c/o act-technik GmbH
Postal address:
Town: Neunkirchen
Postal code: 66538
Country:
Prior information
Contract
Award
Footnote - legal notice

This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.