P-Beja: construction work for dams, canals, irrigation channels and aqueducts
A. Description:
I. Track 1 – free surface channel between the reservoir and the Odearce Sifão Cargo House, 1 786 m of development.
The channel has a trapezoidal section with a track width of 2 m, the slope of the backrests is 1 (V): 1,5 (h) shall be made of metal fibre concrete, designed for a flow rate of 11.36 m³/s and a longitudinal slope of the track of 25 cm/km;
II. Section 2 – between the front loading chamber and the 1.256 m long Selmes reservoir bypass, DN 2 500 mm and a dimensioning flow rate of 11.36 m³/s; nominal diameter and dimensioning flow rate of 9.5 m³/s;
v. Track 6 – between section 5 and the 173 m extension watershed tower DN 2 500 mm and a size of 9.5 m³/s (this section is defined in the Saint-Pedro dam project);
VI. Section 7 – between the end of section 2 and the bypass for the Paço dam, with a development of 3 454 m, nominal diameter of 1 300 mm and a dimensioning flow rate of 1.41 m³/s;
VII. Section 8 – between section 7 and the bypass for Monte das Cortes de Cima, with a length of 551 m DN 1 200 mm and a dimensioning flow rate of 1.31 m³/s;
VIII. Section 9 – between section 8 and the bypass for Mount of Malheiro, with 1 164 m of development, DN 1 200 mm and a dimensioning flow rate of 1.30 m³/s;
IX. Section 10 – between section 9 and Selmes reservoir, 348 m in development, DN 1 200 mm and a size flow rate of 1.30 m³/s (the last part of this section is defined in the Selmes Reserve Implementation Project;
X. Track 12 – Fertiliser of the Quinta de São Pedro – derivation of the main fertiliser to feed the Quinta de São Pedro dam, 117 m long, nominal diameter 400 mm and a design flow rate of 0.15 m³/s;
XI. Section 13 – Fertiliser of Monte do Paço – derivation of Selmes fertiliser to supply the Paço dam, 5.263 m in development, nominal diameter 500 mm and a size flow of 0.1 m³/s;
XII. Section 14 and 15 – Fertiliser of Monte das Cortes de Cima – drift to feed the Monte das Cortes de Cima block, 2 208 m in development. In this fertiliser there will be a small derivation for Monte das Cortes de Baixo, so it will consist of two sections: section 14 with development 264 m, nominal diameter 560 mm and a dimensioning flow rate of 0.26 m³/s; and section 15 with a development of 1.944 m and a nominal diameter of 500 mm and a dimensioning flow rate of 0.2 m³/s;
XIII. Section 16 – Fertiliser of the Mount do Malheiro – a bypass for feeding the Monte Malheiro block with a development of 400 m, nominal diameter 689 mm and a dimensioning flow rate of 0.11 m³/s;
XIV. Section 17 – Fertiliser of the Mountain Weights – Albufeira do Peso supply line from the Pedrogon reservoir, 2 426 m of development, nominal diameter 355 mm and a size flow rate of 0.10 m³/s;
XV. Section 18 – Fertiliser of Monte das Aldeias – supply line to Monte das Aldeias from the Pedrógon reservoir, 416 m of development, nominal diameter 355 mm and a size flow rate of 0.13 m³/s;
2. S. Pedro dam.
A. Description:
I. The Barrage of S. Pedro will be built in landfills with an zoned profile and sealing the foundation by means of injections curtain. With a maximum height of approximately 24 m above the land, crown 7 metres wide and total landfill volume estimated at 400 000 m³;
II. Concrete surface discharger, with WES single labirine-type discharger, in front position; rectangular discharge channel terminating in a type of energy sink;
III. Water Taking tower with rectangular section of concrete, with a single main abstraction level and an ecological flow intermediate; grill and wagon holder; walkway access with a length of approximately 50 m and 2 pillars;
IV. Bottom discharge and ecological flow in its own circuit, parallel to the provisional diversion, including hollow jet valve and ring type valve;
v. Water supply circuit, starting at the water inlet, passes through the landfill in a duct DN 2500 concrete together with the water inlet and bottom discharge pipes;
VI. Water inlet circuit based on the infrastructure of the interim diversion phase;
VII. Provisional deviation comprising a section of circular section founded under the landfill between the water inlet tower and a dissipation basin of 170 metres;
VIII. Equipment, electrical installations and communication. Accessibility and installation of the observation plan.
This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.