F-Lille: roadworks
The works consist of the carrying out of a turning point close to the works carried out in phase 1 as part of operation Doi001 Deviation of RD 120 on the territory of the municipality of Auby.
The demolition and reconstruction of the works of art crossing the Canal de la Deûle, i.e. from 2.7.2012 to 2.9.2012, given that the works will continue until the end of the 120-day execution period.
During this period, road and pedestrian traffic will be prohibited under RD 120 under works law. The maximum cut-off for all road and pedestrian traffic on RD 120 is as follows:
— From 1.7.2012-18: 30,
— At 2.9.2012-18: 30.
The contractor must comply with the reopening to all traffic (road and pedestrian) on RD 120 from 2 September 2012, given that the works will continue until the end of the 120-day execution period.
A separate contract will be awarded for each lot. The terms referred to in Article II.3 of this notice are supplemented by those indicated in Article II.3 of the Consultative Rules. The contract is not divided into tranches.
Estimated date of commencement of services: 2.7.2012.
This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.