Published14/11/2019
-
Deadline19/12/2019
-
Awarded24/02/2020
-
Today06/08/2026
Utilities
- indicates text translated automatically in your browsing language
France-La Roche-sur-Yon: Viaduct construction work
The subject of this contract is earthworks, works of art and restoration of communications on the crossing of La Vie, in connection with the 2x2 lanes of RD 948 on the Bel Air/La Vie section.
— demolition of carriages 1 515 m³,
— ground pickling 42 730 m²,
— spoil/backfill of the site 15 720 m³,
— excavated excavated for infants,
— merlons, modelled 6 090 m³,
— input backfill implemented 23 200 m³,
— serious untreated 7 070 m³,
— concrete frame 250 x 250 cm 35 m,
— concrete pipes 420 m,
— slotted gutters 640 m,
— very thin bituminous concrete 10 855 m²,
— semi-granu bituminous concrete 690 m³,
— serious bitumen 1 505 m³,
— single-layer coating 13 200 m²,
— attachment layer 30 855 m²,
— rabotage 9 720 m²,
461 m³ landfill excavations,
— spoil under viaduc in infants,
— merlons, modelled 19 910 m³,
— excavation backfill in 0/63 930,
— vertical pike drilling 9.
http://marchespublics.vendee.fr
Postal address: 35/37 rue Christian Huygens
Town: Tours
Postal code: 37100
Country: FRA
This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.