F-Rouen: structural engineering consultancy services
Project management contract (building area) within the meaning of Law MOP 85.704 of 12.7.1985 as amended by Law No 88.1090 of 1.12.1988 and Decree No 93.1268 of 29.11.1993, the Order of 21.12.1993 on technical arrangements for the implementation of project management elements and Order No 2004-566 of 17.6.2004 amending Law 85-704 of 12.7.1985.
This certificate shall identify the following:
Basic mission extended to executive studies with summary.
Additional tasks:
— coordination steering authorisation assignment (OPC);
— SSI coordination mission.
Purpose of the operation.
Reminder of the objectives of the operation:
— abolition of temporary buildings;
— creation of 5 banked rooms in the pre-existing building;
— creation of an extension of approximately 100 M2 in front closed in order to recreate the relaxation/play space existing in the current preau,
— removal of the patio from the CDI in order to recover space of approximately 49 m²,
— extension of the existing multipurpose room,
— creation of a meeting room and 2 parents’ offices,
— fitting-out of sanitary facilities,
— redistributing the existing premises of the Science Hub,
— resise and rationalise the banalised rooms,
— covering of facades and roofs of terraces.
Areas excluding new net work: 719 m².
Restructured areas excluding net work: 1 234 m².
Provisional deadline for the execution of the works: A maximum of 24 months (including 2 months of preparation).
Provisional method of devolution of work: separate shape bodies.
Provisional date of commencement of studies: September – October 2010 for a duration of 35 weeks, i.e. a maximum of 8 months.
Provisional date of commencement of work: December 2011 – January 2012.
Estimated cost of the works as a guide: EUR 3 246 474 excl. tax (value July 2009).
Duration of the contract or period of performance: 39 months from the notification of the contract.
F-
This content published on this page is meant purely as an additional service and has no legal effect. The Union's institutions do not assume any liability for its contents. The official versions of the relevant tendering notices are those published in the Supplement of Official Journal of the European Union and available in TED. Those official texts are directly accessible through the links embedded in this page. For more information please see Public Procurement Explainability and Liability notice.