DK-Gentofte: Maskiner og apparater til filtrering eller rensning af gasser - EU-udbud
DisplayCustomHeader
Procurement Detail Actions Portlet
OP Portal - Procurement - Details

DK-Gentofte: Maskiner og apparater til filtrering eller rensning af gasser

  • Offentliggjort
    11/10/2011
  • Frist
    31/10/2011
  • Tildelt
    09/02/2012
  • I dag
    14/08/2026
Status
Tildelt
Kontrakttype
Supplies
Genstand for fornyelse
No
Indkøber
Ikke til rådighed
Udførelsessted
NUTS code: DK042 Østjylland
Indkøbers beliggenhed
NUTS code: Ikke til rådighed
Sektor (hoved-CPV)
42514000 Maskiner og apparater til filtrering eller rensning af gasser
Samlet anslået kontraktværdi (ekskl. moms)
Ikke til rådighed
Samlet endelig kontraktværdi (ekskl. moms)
Ikke til rådighed
Referencenummer for tilbuddet
2-00381
Beskrivelse

The main data of the existing plant are as follows:
1. Flue gas amount: 71,5 kg/s;
2. Gas turbine, model GE LM250PE;
3. Degasification type: Aalborg Ciserv A/S LV24;
4. Current NOx level, both with and without water injection:
a) Without water injection: 1 100 mg/Nm3;
b) With water injection: 680 mg/Nm3.
The new SCR (selective catalytic reduction) plant must comply with the following requirements:
5. The following emissions must as a minimum be observed after installation and commissioning. When determining the level of NOx emission, all NOx must be converted into NO2. In practise, the emission of NO and NOx is measured in ppm. The found values must be added up and the sum must be converted into mg/normal m3 NO2 by the use of the conversion factor for NO2.
— The NOx emission must be kept under 150mg/Nm3 (reference state: 5 % 02, 0 degrees Celsius, 101.3 kPa, dry gas under all operational conditions,
— The ammonia emission must be kept under 12mg/Nm3 (reference state: 5 % 02, 0 degrees Celsius, 101.3 kPa, dry gas under all operational conditions.
The following is included in the supply:
— The existing ammonia storage must be used (24 % dissolution, (NH3) in connection with the installation of the plant,
— Pipe routing, pumps and electrical installation as regards connection to existing ammonia storage,
— Assembly and installation in the time frame (May 2012, June 2012, July 2012),
— Commissioning in the time frame (August 2012). Must be able to comply with emission requirements as of 1.9.2012,
— Scaffolding, insulation in connection with assembly and installation,
— Commissioning,
— Documentation Electronic + 2 x hard copy,
— Operational description (maintenance manuals) electronic + 2 x hard copy,
— C&I concept for control system (Siemens T-3000),
— Third party control and verification of emissions in connection with commissioning,
— KKS numbering of drawings, components, pipe routing and cables.

Indsendelsesmetode
Ikke til rådighed
Tilbud kan afgives
Submission for all lots
Oplysninger om en offentlig kontrakt, en rammeaftale eller et dynamisk indkøbssystem
Bekendtgørelsen vedrører en offentlig kontrakt
Fremgangsmåden ved åbning af tilbud (dato)
Ikke til rådighed
Udførelsessted
Tildelingsmetode
The most economic tender
Anslået værdi
Ikke til rådighed
Endelig kontraktværdi
Ikke til rådighed
Tildeling af kontrakten
Officiel betegnelse: Industrivarme
Postadresse: Landholmvej 12
By: Storvorde
Postnummer: 9280
Land: DNK
Forudgående oplysninger
Kontrakt
Tildeling
Footnote - legal notice

Det indhold, der offentliggøres på denne side, er udelukkende tænkt som en supplerende tjeneste og har ingen retsvirkning. EU's institutioner påtager sig intet ansvar for dens indhold. De officielle udgaver af de relevante udbudsbekendtgørelser er dem, der er offentliggjort i tillægget til Den Europæiske Unions Tidende og findes i TED. Disse officielle tekster er tilgængelige direkte via linkene på denne side. Yderligere oplysninger findes i meddelelsen om udbudsbetingelser og ansvar.